2004-0817CA technical archives www.trictrenchless.com TRIC Training Log: 08-17-04 Demo Team: Beyond Plumbing, Oakland, CA Job: Two homes opposite each other connecting to main (one hole in street at main, lateral connections 2 feet apart) Pull: (2) downhill / 40’ each / 4” SDR17 replacing 4” VCP

Upload: tric-tools

Post on 12-Jul-2015

349 views

Category:

Business


2 download

TRANSCRIPT

Page 1: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

TRIC Training Log: 08-17-04

Demo Team: Beyond Plumbing, Oakland, CA

Job: Two homes opposite each other connecting to main (one hole in street at main, lateral connections 2 feet apart)

Pull: (2) downhill / 40’ each / 4” SDR17 replacing 4” VCP

Page 2: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

We at TRIC Tools have specific requirements for the use and maintenance of our equipment with regard to safety and efficiency on the job. Our written and verbal recommendations coincide with safety regulations set by local, state, and national government agencies. Our

clients may have standards over and above industry regulations. However, the safety equipment, apparel, and operating procedures

demonstrated by our clients in this presentation may or may not comply with above mentioned government regulations.

Page 3: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

The project: One contract, two homes in Castro Valley. Homes face each other across street, and each is replacing entire lateral from building foundation to main in street.

Page 4: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Pulling hole: Note two connection points to sewer main; upstream (left) connection serves home on west side of street, and downstream connection (right) serves east side home.

Page 5: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Fusing operation: Jig used to join pieces of 4” HDPE pipe on sidewalk.

Page 6: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

East side entry: Preparing to feed pipe into hole at property line.

Page 7: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Pulling hole: Preparing ram to pull from east side home’s property line to main.

Page 8: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

East side entry: Bursting head just beginning to break old pipe.

Page 9: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Monitoring entry: After a good beginning, pipe often needs little attention, save monitoring for traffic obstruction or protecting property and landscaping.

Page 10: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

One hole, two pulls: Disconnecting ram assembly after east side pull.

Page 11: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

“Bumping”: After hydraulic equipment is removed from the pulling hole, pipe is driven further towards final connection.

Page 12: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Final approach: Watching the pipe being driven further towards main.

Page 13: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Main connection #1: Finishing the east side main connection. Note pulley and resistance plate set up to pull the west side lateral.

Page 14: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

West entry hole: Shallow and close to foundation. Cable inserted here and fed through old line to street (pulling) hole.

Page 15: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

West side property line: City requires cleanout at this point. Old VCP (vitreous clay pipe) lateral has been exposed.

Page 16: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

West side property line: Exposed pipe removed, showing pulling cable after being fed through line from house foundation entry hole.

Page 17: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Sewer sermon: TRIC associate explaining the virtues of trenchless technology.

Page 18: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Lateral #2: Setting up ram to pull west side home lateral.

Page 19: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Big Bend: HDPE pipe flexibility demonstrated at west home entry.

Page 20: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Just before tension: PE pipe in position for entry.

Page 21: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Initial guidance: The bursting head assembly “hinges” on the clevis (cable terminator) as pull begins.

Page 22: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Entry: TRIC’s patented head assembly and flexible HDPE pipe make this type of seemingly impossible approach routine.

Page 23: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

The great arc: Bursting head has traveled down the old line a few feet, and new HDPE line has formed the “U-turn” which worker will assist for the duration.

Page 24: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

Close to home: Extreme bend is guided and maintained throughout pull.

Page 25: 2004 0817 Ca

2004-0817CA

technical archives

www.trictrenchless.com

View from the street: A new sewer in progress.