pm-05 - eva

Upload: aristyo-ridwan-rais

Post on 06-Apr-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 PM-05 - EVA

    1/49

    Earned Value Analysis

    Budi Hartonohttp://boed.staff.ugm.ac.id

  • 8/3/2019 PM-05 - EVA

    2/49

    Penjelasan Tugas #3

    2

  • 8/3/2019 PM-05 - EVA

    3/49

    What Is It ?

    Why Do I Need It ?

    How Do I Do It?

    Earned Value Analysis

  • 8/3/2019 PM-05 - EVA

    4/49

    4

    Todays Situation

    Need for accurate and consistent statusinformation

    Numerous complex (and interrelated) projects

    Projects with many WBS activities

    Virtual Offices

    Diverse technology platforms

  • 8/3/2019 PM-05 - EVA

    5/49

    5

    Theres Room For Improvement

    70% of projects are:Over BudgetBehind Schedule

    52% of all projects finish at189% of their initial budget

    And some, after huge investments

    of time and money, are simply nevercompleted

    Source:The Standish Group

  • 8/3/2019 PM-05 - EVA

    6/49

    6

    How to answer the question:Have we done what we said wed do?

    % complete estimating% of Budget spent% of work done% of time elapsed

    subjective, incomplete

    draws false conclusions

  • 8/3/2019 PM-05 - EVA

    7/49

    7

    It tells you how much youve spentand compares it to the budget.

    Does it give an accurate picture ofwhere you are on the project? NO!It doesnt tell you if...

    youre ahead or behind schedule

    youre over or underspent

    youve spent money on the rightthing

    youre getting value for money

    your problems are over or onlyjust begun

    Whats missing?

    time

    Project Mgt in the dark

  • 8/3/2019 PM-05 - EVA

    8/49

    8

    Accomplishment is (planned)

    work that has been carriedout successfully.

    The budgeted cost of thatwork quantifies the

    accomplishment. This is called earned value

    time

    Whats missing?

    - knowing how much has been accomplished

  • 8/3/2019 PM-05 - EVA

    9/49

    9

    Enter Earned Value Analysis

    Earned Value Analysis is: an industry standard way to:

    measure a projects progress, forecast its completion date and final cost, and

    provide schedule and budget variances along theway.

    By integrating three measurements, it provides

    consistent, numerical indicators with which you canevaluate and compare projects.

  • 8/3/2019 PM-05 - EVA

    10/49

    10

    Whats more Important?

    Knowing where you areon Schedule?

    Knowing where you areon Budget?

    Knowing where you areon Work Accomplished?

  • 8/3/2019 PM-05 - EVA

    11/49

    11

    EVA Integrates All Three

    It compares the PLANNED amount of workwith what has actually been COMPLETED, todetermine if COST, SCHEDULE, andWORK

    ACCOMPLISHEDare progressing asplanned.

    Work is Earned or credited as it is

    completed.

  • 8/3/2019 PM-05 - EVA

    12/49

    12

    Earned Value needed because...

    Different measures of progress fordifferent types of tasks

    Need to roll up progress of manytasks into an overall project status

    Need for a uniform unit of measure

    (dollars or work-hours).

  • 8/3/2019 PM-05 - EVA

    13/49

    13

    Earned Value needed because...

    Provides an Early Warning signal for prompt

    corrective action.

    Bad news does not age well.

    Still time to recover

    Timely request for additional funds

  • 8/3/2019 PM-05 - EVA

    14/49

    14

    And One More Reason

    Why You Need EVA

    ?

  • 8/3/2019 PM-05 - EVA

    15/49

    15

    In the US, it is a must

    These Set the Stage:

    GPRA; 1993

    FASA, Title V; 1994

    Clinger-Cohen Act; 1996

    And Then Along Came OMB! (Circular A-11, Part 7)

    "Agencies must use a performance based acquisitionmanagement system, based on ANSI/EIA Standard748, to measure achievement of the cost, schedule,and performance goals."

  • 8/3/2019 PM-05 - EVA

    16/49

  • 8/3/2019 PM-05 - EVA

    17/49

    17

    So, Is This Stuff New ?

    Its been around since the sixties.

    Cost/Schedule Control Systems Criteria

    (C/SCSC)

  • 8/3/2019 PM-05 - EVA

    18/49

    18

    Examples of informal Earned Value Analysis

    Its done informally without realizing it.30% time used,30% $$ spent

    So, if 30% of the work is done, I must be OK ??

    Shop floor estimates

    Cost Comparisons

    Budget vs. Actual

  • 8/3/2019 PM-05 - EVA

    19/49

  • 8/3/2019 PM-05 - EVA

    20/49

  • 8/3/2019 PM-05 - EVA

    21/49

    21

    But First! - We gotta get organized

    EVA works best when work is compartmentalized.

    Compartmentalization is best achieved with a well-planned Work Breakdown Structure.

    So, how do I create a WBS for a really complexproject?

  • 8/3/2019 PM-05 - EVA

    22/49

    22

    Obviously in small bites.

    How am I gonna eat this elephant?

  • 8/3/2019 PM-05 - EVA

    23/49

    23

    Proper WBS Design

    One WBS Deliverable-oriented Work not in the WBS is out-of-scope Each descending level represents more detail

    Full (and accurate) definition is key Defined deliverable(s) Timeframe for delivery of product

    Total cost (direct and indirect) to deliver product

    Lets Look at an example:

  • 8/3/2019 PM-05 - EVA

    24/49

    24

    A sample Work Breakdown Structure

    Serve Pizzas to Customers

    Provide the Place Cook the Food Serve Customers (Others)

    Cook the SauceMake the Dough Build the Pizza

  • 8/3/2019 PM-05 - EVA

    25/49

  • 8/3/2019 PM-05 - EVA

    26/49

  • 8/3/2019 PM-05 - EVA

    27/49

  • 8/3/2019 PM-05 - EVA

    28/49

    28

    WBS Units are Work Packages

    Lowest level WBS elements

    Have three measurable components

    Scope of work to be accomplished Total (direct and indirect) cost Timeframe for completion

    Too large and you have multiple people responsible for thework.

    Too small and the program manager winds up micro-

    managing everything.

  • 8/3/2019 PM-05 - EVA

    29/49

  • 8/3/2019 PM-05 - EVA

    30/49

    30

    Some New Terms

    BCWS - Budgeted Cost of Work Scheduled

    ACWP - Actual Cost of Work Performed

    BCWP - Budgeted Cost of Work Performed

  • 8/3/2019 PM-05 - EVA

    31/49

  • 8/3/2019 PM-05 - EVA

    32/49

    32

    BCWS - Budgeted Cost of Work Scheduled

    0

    20000

    40000

    60000

    80000

    100000

    120000

    Jan-03

    Feb-03

    Mar-03

    Apr-03

    May-03

    Jun-03

    Jul-03

    Aug-03

    Sep-03

    Oct-03

    Nov-03

    Dec-03

    BCWS

  • 8/3/2019 PM-05 - EVA

    33/49

    33

    Earned Value Definitions (cont.)

    ACWP: Actual Cost of Work Performed

    Cost incurred to accomplish the work that has been

    done to date.

  • 8/3/2019 PM-05 - EVA

    34/49

    34

    ACWP -Actual Cost of Work Performed

    49000

    56000

    0

    20000

    40000

    60000

    80000

    100000

    120000

    Jan-0

    3

    Feb-0

    3

    Mar-0

    3

    Apr-0

    3

    May-0

    3

    Jun-0

    3

    Jul-0

    3

    Aug-0

    3

    Sep-0

    3

    Oct-0

    3

    Nov-0

    3

    Dec-0

    3

    BCWP

    ACWP

    OK, were 7K over budget, is that bad

  • 8/3/2019 PM-05 - EVA

    35/49

    35

    Earned Value Definitions (cont.)

    BCWP: Budgeted Cost of Work Performed

    The planned (not actual) cost to complete the work that

    has been done.

    Note that this is the cost of the workperformed and,it is the budgeted amount, notthe actual amount.

  • 8/3/2019 PM-05 - EVA

    36/49

    36

    BCWP - Budgeted Cost of Work Performed

    49000

    55000

    0

    20000

    40000

    60000

    80000

    100000

    120000

    Jan-03

    Feb-03

    Mar-03

    Apr-03

    May-03

    Jun-03

    Jul-03

    Aug-03

    Sep-03

    Oct-03

    Nov-03

    Dec-03

    BCWP

    BCWS

    The project is behind schedule.

    The Whole Story

  • 8/3/2019 PM-05 - EVA

    37/49

    37

    55000

    49000

    56000

    0

    20000

    40000

    60000

    80000

    100000

    120000

    Jan-03

    Feb-03

    Mar-03

    Apr-03

    May-03

    Jun-03

    Jul-03

    Aug-03

    Sep-03

    Oct-03

    Nov-03

    Dec-03

    BCWS

    BCWP

    ACWP

    The Whole Story

    And heres the full picture.

    The project is over budget by 7k dollars.Weve only gotten 49 thousand dollars worth of work down.

    And what does that mean? - - - (were behind schedule.)

  • 8/3/2019 PM-05 - EVA

    38/49

  • 8/3/2019 PM-05 - EVA

    39/49

    39

    time

    CV

    SV

    CV (Cost Variance)

    BCWP - ACWP

    earned value - actual cost SV (Schedule Variance)

    BCWP - BCWS

    earned value - planned

    value 0 once all work completed

    Variance

  • 8/3/2019 PM-05 - EVA

    40/49

  • 8/3/2019 PM-05 - EVA

    41/49

    41

    Schedule Variance & Cost Variance

    Schedule Variance = BCWP-BCWS

    $49,000- 55,000

    SV = - $ 6,000

    Cost Variance = BCWP-ACWP

    $49,00056,000

    CV = - $7,000

  • 8/3/2019 PM-05 - EVA

    42/49

    42

    SPI: Schedule Performance Index

    SPI=BCWP/BCWS

    SPI

  • 8/3/2019 PM-05 - EVA

    43/49

    43

    CPI (Cost Performance

    Index) BCWP/ACWP

    earned/actual

    the one to use

    SPI (SchedulePerformance Index)

    BCWP/BCWS

    earned/planned

    of diminishing value asproject progressestends to 1

    1.1

    0.9

    0.8

    1.0

    1.1

    0.9

    0.8

    1.0

    CPI

    SPI

    Performance Indices

  • 8/3/2019 PM-05 - EVA

    44/49

    44

    Performance Metrics

    SPI: BCWP/BCWS

    49,000/55,000 = 0.891

    CPI: BCWP/ACWP

    49,000/56000 = 0.875

    CSI: SPI x CPI

    .891 x .875 = 0.780

  • 8/3/2019 PM-05 - EVA

    45/49

  • 8/3/2019 PM-05 - EVA

    46/49

    46

    PMBOK

    Estimate at Completion (EAC) =

    1. AC+ETC (when original estimates areconsidered flawed)

    2. AC+BAC-EV (when everything is OK andvariance will not occur in the future)

    3. AC+((BAC-EV)/CPI) (when everything is

    OK and variance will occur in the future)

  • 8/3/2019 PM-05 - EVA

    47/49

    47

    102000

    90882

    103865

    0

    20000

    40000

    60000

    80000

    100000

    120000

    Jan-03

    Feb-03

    Mar-03

    Apr-03

    May-03

    Jun-03

    Jul-03

    Aug-03

    Sep-03

    Oct-03

    Nov-03

    Dec-03

    BCWS

    BCWP

    ACWP

    Making ProjectionsThe Situation at Year-End (Not Project Completion)

  • 8/3/2019 PM-05 - EVA

    48/49

    48

    Notes from previous slide

    We can expect to finish the year having spent a bit more

    than was budgeted.

    But look at the ACWP curve: We have only delivered89% of the product

    but weve spent everything we had, plus more.

    Final line? Without a change in performance, we wouldhave to spend an additional 28% of our budget tocomplete the job.

    Why 28% when were only 11% behind? Because our

    Cost/Schedule Index says we will only be able to performto a 78% level, and well continue to fall behind.

    E i C l

  • 8/3/2019 PM-05 - EVA

    49/49

    49

    Estimate to Complete

    102000

    116,571

    0

    20000

    40000

    60000

    80000

    100000

    120000

    140000

    Jan-03

    Mar

    -03

    May

    -03

    Jul-0

    3

    Sep-03

    Nov-0

    3

    Jan-04

    Mar

    -04

    BCWS

    BCWP

    ACWP