TRIC Training Log: 05-13-04
Client: West Point SolutionsJob: Dynasty Restaurant, Valco Mall, Santa Clara, CAPull: upstream / 140’ / 6” / SDR17 / replacing 6” C.I.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
We at TRIC Tools have specific requirements for the use and maintenance of our equipment with regard to safety and efficiency on the job. Our written and verbal recommendations coincide with safety regulations set by local, state, and national government agencies. Our
clients may have standards over and above industry regulations. However, the safety equipment, apparel, and operating procedures
demonstrated by our clients in this presentation may or may not comply with above mentioned government regulations.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
When fusing long sections of pipe, keep in mind eventual entry point of bursting head (shown attached to clevis head for demonstration; leave bursting head off while fusing).
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Multiple interior excavations to uncover plumbing connection points. Green dashed line shows path of pull under dining area.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Path of pull under kitchen.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Preparing pulling hole.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Drawing cable upstream to pulling hole with duct rod.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Moving pipe to entry point.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
The more the merrier!
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Parking lot exit lane is blocked off to facilitate pull.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
140’ ready to go!
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Inching along…
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Breaking out old pipe at pulling end.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Cribbing soft earth at pulling end. Wood is braced between dirt wall and pressure plate to distribute load.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
When wood is insufficient, steel poles are driven into the ground instead to stabilize pulling equipment.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Managerial review…
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Unnecessary clutter at entry!
2004-0513CA.ppt
technical archives
www.trictrenchless.com
This is how NOT to start a pull.
Actual entry point
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Get rid of the clutter! Shown here at entry are at least six to eight bands and couplings, including a vertical stack, that will only be dragged into the earth and
become one big obstruction. Band cutting blade attached to bursting head functions only when pipe is part of an undisturbed system that is secured underground.
Actual entry point
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Due diligence…
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Clean entry!
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Removing exposed bands, couplings, and connections in middle open trench…
2004-0513CA.ppt
technical archives
www.trictrenchless.com
…to avoid inevitable “traffic jam” of loose (uncovered) connections being pushed along rather than burst away.
2004-0513CA.ppt
technical archives
www.trictrenchless.com
Remove all exposed pipe, bands, and connections in bursting path. This material will only create problems by cluttering the bursting head.