PROJECT PORTFOLIO

SURESH BABU GB.E (MECHANICAL)

REVIT MEP, HVAC ENGINEERsureshgvr91@gmail.com

Contact. No: +91-8050575673

PROJECT OVERVIEW

Building type: Office Building

Location: Bangalore.

Building Load:350 TR

Area: 217900 Square ft.

Floors: Ground floor + 6Floors.

Design occupancy: 3010 Peoples.

Building operating schedule: 12x5.

Air distribution system: VAV single duct.

TYPICAL FLOOR PLAN

TYPICAL FLOOR 2D VIEW TYPICAL FLOOR 3D VIEW

Created walls, columns in the model. Placed windows, doors and curtain walls. Created Spaces, Zones, & color fill legend.

3D VIEW OF BUILDING

HEAT LOAD REPORT

DUCT PRESSURE DROP ANALYSIS

Static Pressure for critical path is 28.5 Pa Based on pressure drop in Critical path

AHU fan is selected

2D VIEW 3D View

3D View

PHE & PRESSURE DROP ANALYSIS

FIRE PROTECTION SYSTEM

SPRINKLER

2D IEW3D VIEW

ELECTRICAL CABLE ROUTING

3D VIEW2D VIEW

False Ceiling levelLighting FixtureSupply Diffuser

SECTIONAL VIEWS

3D Sectional View

CO-ORDINATION OF ALL FLOORS

3D VIEW OF MEP OF ALL 7 FLOORS

CLASH DETECTION REPORT

CLASH DETECTION & SOLUTION

Clash in between cable tray & domestic hot water pipe.

Clash solved by moving domestic hot water pipe

2D VIEW 3D VIEW

CLASH

CLASH DETECTION & SOLUTION

Clash in between duct & cable tray.

Clash solved by moving cable tray.

Clash in between duct & column.

Clash solved by moving duct.

ANNOTATION

DUCT PRESSURE LOSS REPORT

BILL OF QUANTITITES

DRAFTING SHEET ORIENTATION

THANK YOU