abhinav prakash

Upload: abhinav-prakash

Post on 04-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Abhinav Prakash

    1/10

    FAST TRACK CONSTRUCTION:

    Firstly BOLT was tried in 1997.

    Later on it decided to go for BOT scheme in 2000-

    01.

    Work started in 2002: approx. 2 years.

    Completed on 2004.

    Good achievement but the time taken was too

    much.

    BOT schemes are good for a new project.

  • 7/30/2019 Abhinav Prakash

    2/10

    QUALITY OF CONSTRUCTION:

    Lower construction costs, reduced life cycle

    maintenance costs & lower costs of associated risks:

    PPPs.

    Long term operation & maintenance responsibilities

    to the private sector: in traditional contracting.

    Reduces the risk of future fluctuations in operation

    costs.

    In this case not much benefits could be drawn, only

    final quality of project was better due to high cost.

  • 7/30/2019 Abhinav Prakash

    3/10

    NATURE OF FUNDING:

    Estimated cost was Rs 70 crores in 2001.

    Debt equity ratio: 2.75 & Rs 50 cr. from long term

    bank & rest from promoters equity.

    Various bids were invited & the lowest bid of Rs

    7.96 cr. with IRR of 16.27% was awarded the

    project.

    Due to inflation risk & additional liability the cost

    incurred upto Rs 92 cr. with IRR upto 12% only.

    12% IRR considered good return to SPC & it is not a

    very high cost for railways.

  • 7/30/2019 Abhinav Prakash

    4/10

    IMPLICATIONS:

    OPERATIONAL Deputy Chief Engineer of engineering dept. was nodal

    officer to interact the project.

    Various disputes & conflicts took place such as:

    Delay in finalysing yard plans & its signal interlockingpans.

    Delay in traffic blocks for movement of material &alterations in yards.

    Delay in materials like rails, sleepers, switches, etc from

    RDSO.

  • 7/30/2019 Abhinav Prakash

    5/10

    CONTRACTUAL

    It was specified that track would be made for 100

    KMPH to the satisfaction of CRS & make up of

    earthwork also.

    The concessionaire was interested only in shortterm objectives.

    The main objective was to address the specifying

    the quantity of work & quality of materials to beused.

    Through this the possibility of SPC going low quality

    work can be avoided.

  • 7/30/2019 Abhinav Prakash

    6/10

    LEGAL

    The legal dispute occurs because of differentinterpretations by concessionaire & the dept.

    According to concessionaire, concession period

    starts from appointed date i.e. date of finance close

    & access charge become payable from the date of

    COD.

    Finally point of concessionaire has been accepted.

  • 7/30/2019 Abhinav Prakash

    7/10

    Risk Management

    1. Demand Risk Railway operation has the monopoly of railways

    This project is a broken link and having other alternative

    2 Construction Risk-

    Performance guarantee deposit Rs 5 crore

    Completion period was linked with bonus and penalty clauses

    3 Supply Risk-

    Monopoly of railway

    Inspection of RDSO (Railway Design Standards Organization) ismandatory before using material

    Lack of supplier

  • 7/30/2019 Abhinav Prakash

    8/10

    Risk cont..

    4 Human Resource Risk

    Lack of availability of trained manpower.

    5 Design Risk-

    Negligence in the design work

    Principal agent conflict-

    Complex nature of work

    6 Project Management Risk-

    Detailed sequencing of project was done

    Mile stones were made

  • 7/30/2019 Abhinav Prakash

    9/10

    Contd

    7 Inflation Risk-

    Major items had inflated between the date of RFP and to real

    execution

    For example- Rail, Ballast, Sleeper had inflated from 31000/MT to

    35458/ MT

    8 Maintenance Risk-

    Requirement to maintain a level of standard for design and standard

    work

    Warranty of 12 month

    9 Regulation Risk

    Risk is shared between Railways and concessionaire as per clause

  • 7/30/2019 Abhinav Prakash

    10/10

    Contd

    10 Risk of obtaining clearances from other agencies-

    Railways has taken the responsibility of getting clearances from otheragencies to protect the concessionaire.

    11 Future cash flow risk-

    Risk of default in getting annuity from the Railways

    12 Land acquisition Risk-

    Land acquisition was the responsibility of Railways

    13 Force majeure risk-

    Risk of politician and non politician