abhinav prakash
TRANSCRIPT
-
7/30/2019 Abhinav Prakash
1/10
FAST TRACK CONSTRUCTION:
Firstly BOLT was tried in 1997.
Later on it decided to go for BOT scheme in 2000-
01.
Work started in 2002: approx. 2 years.
Completed on 2004.
Good achievement but the time taken was too
much.
BOT schemes are good for a new project.
-
7/30/2019 Abhinav Prakash
2/10
QUALITY OF CONSTRUCTION:
Lower construction costs, reduced life cycle
maintenance costs & lower costs of associated risks:
PPPs.
Long term operation & maintenance responsibilities
to the private sector: in traditional contracting.
Reduces the risk of future fluctuations in operation
costs.
In this case not much benefits could be drawn, only
final quality of project was better due to high cost.
-
7/30/2019 Abhinav Prakash
3/10
NATURE OF FUNDING:
Estimated cost was Rs 70 crores in 2001.
Debt equity ratio: 2.75 & Rs 50 cr. from long term
bank & rest from promoters equity.
Various bids were invited & the lowest bid of Rs
7.96 cr. with IRR of 16.27% was awarded the
project.
Due to inflation risk & additional liability the cost
incurred upto Rs 92 cr. with IRR upto 12% only.
12% IRR considered good return to SPC & it is not a
very high cost for railways.
-
7/30/2019 Abhinav Prakash
4/10
IMPLICATIONS:
OPERATIONAL Deputy Chief Engineer of engineering dept. was nodal
officer to interact the project.
Various disputes & conflicts took place such as:
Delay in finalysing yard plans & its signal interlockingpans.
Delay in traffic blocks for movement of material &alterations in yards.
Delay in materials like rails, sleepers, switches, etc from
RDSO.
-
7/30/2019 Abhinav Prakash
5/10
CONTRACTUAL
It was specified that track would be made for 100
KMPH to the satisfaction of CRS & make up of
earthwork also.
The concessionaire was interested only in shortterm objectives.
The main objective was to address the specifying
the quantity of work & quality of materials to beused.
Through this the possibility of SPC going low quality
work can be avoided.
-
7/30/2019 Abhinav Prakash
6/10
LEGAL
The legal dispute occurs because of differentinterpretations by concessionaire & the dept.
According to concessionaire, concession period
starts from appointed date i.e. date of finance close
& access charge become payable from the date of
COD.
Finally point of concessionaire has been accepted.
-
7/30/2019 Abhinav Prakash
7/10
Risk Management
1. Demand Risk Railway operation has the monopoly of railways
This project is a broken link and having other alternative
2 Construction Risk-
Performance guarantee deposit Rs 5 crore
Completion period was linked with bonus and penalty clauses
3 Supply Risk-
Monopoly of railway
Inspection of RDSO (Railway Design Standards Organization) ismandatory before using material
Lack of supplier
-
7/30/2019 Abhinav Prakash
8/10
Risk cont..
4 Human Resource Risk
Lack of availability of trained manpower.
5 Design Risk-
Negligence in the design work
Principal agent conflict-
Complex nature of work
6 Project Management Risk-
Detailed sequencing of project was done
Mile stones were made
-
7/30/2019 Abhinav Prakash
9/10
Contd
7 Inflation Risk-
Major items had inflated between the date of RFP and to real
execution
For example- Rail, Ballast, Sleeper had inflated from 31000/MT to
35458/ MT
8 Maintenance Risk-
Requirement to maintain a level of standard for design and standard
work
Warranty of 12 month
9 Regulation Risk
Risk is shared between Railways and concessionaire as per clause
-
7/30/2019 Abhinav Prakash
10/10
Contd
10 Risk of obtaining clearances from other agencies-
Railways has taken the responsibility of getting clearances from otheragencies to protect the concessionaire.
11 Future cash flow risk-
Risk of default in getting annuity from the Railways
12 Land acquisition Risk-
Land acquisition was the responsibility of Railways
13 Force majeure risk-
Risk of politician and non politician