2 jayanti vadoda

Upload: afolabi-eniola-abiola

Post on 01-Jun-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 2 Jayanti Vadoda

    1/37

    ESSAR OIL VADINAR REFINERY

    Mega Turnaround Sept-Oct 2011

    A Bench Mark in the Ref in ing sector looking

    at the large Work-scope wh ich was com pleted

    wi th c ompressed engineer ing days and

    then fast track star t-up of the uni ts

  • 8/9/2019 2 Jayanti Vadoda

    2/37

    Definition :

    In petroleum refining  , turnaround means a

    scheduled large-scale maintenance activity wherein

    an entire process unit is taken off stream for anextended period for comprehensive revamp and

    renewal. This operation involves a lot of preparations

    and requires many precautions, especially at during

    startup. 

    Turnaround Maintenance

    http://www.answers.com/topic/oil-refinery-1http://www.answers.com/topic/oil-refinery-1http://www.answers.com/topic/oil-refinery-1http://www.answers.com/topic/oil-refinery-1

  • 8/9/2019 2 Jayanti Vadoda

    3/37

  • 8/9/2019 2 Jayanti Vadoda

    4/37

    Aligned with business goals

    Clear, unambiguous and prioritized

    Measurable, objective and monitored

    Based on experience , scope, knowledge and

    data

    Aggressive but achievable

    Deliberated and agreed to key stakeholders

    Criteria for T/A Objectives

  • 8/9/2019 2 Jayanti Vadoda

    5/37

    + Make plant safe to operate till next outage.

    +  Improve efficiency & throughput of plant by suitable modification.

    +  Reduce routine maintenance costs

    +  Perform Regulatory Inspection

    +  Increase reliability / availability of equipment during operation

    +  Re-establish Plant Capacity .

    +  Upgrade technology by introducing modern equipment &Technology

    +  Complete corrective /preventive maintenance & project work

    Turnaround Objective / Purpose

  • 8/9/2019 2 Jayanti Vadoda

    6/37

  • 8/9/2019 2 Jayanti Vadoda

    7/37

    Turnaround Organization - September 2011Sr.No.  Function  Name 

    1  Head-Refinery C Manoharan 2  Chief Turnaround Manager Narada Singh

    3  Overall Operation Co-Ordinator   KC Swain 

    4  Tech.Services Co-Ordinator   Satheesan V N 

    5  Construction Co-Ordinator   G G Mehta (EPIL) 

    6  HSEF  Dr Gopal Jayaraman 

    7  Turnaround manager   P Rambabu

    8  Turnaround planning Co-Ordinator   D D Chaudhari / Jayanti Vagdoda 

    9  Turnaround-MIS-Co-Ordinator   Hembala Dixit 

    10  Operation Co-Ordinator   ISBL: SKM Rahman/Utility: Chitti Babu/PIT/COT: Ajay Veer  

    11  Engineering & Inspection Ramesh Kumar  

    12  Revamp/Expansion Project Manager   Ramakrishna Paramhans (EPMCL) 

    13 Revamp/Expansion Execution

    Manager  Sudhir Porichha (EPIL) 

    14  Overall Tie-ins Co-Ordinator   Rakesh Kumar  

    15  Instrumentation  S. Laxminarayan 

    16  Electrical  Rajeev Kumar  

    17  Civil   Ashok Srivastava 

    18  EPS  Dhaval Doshi 

    19  Security  Cmdt. Raghuraman 

    20   Admin  Geojo Paul 21 Reliability/Rotary/ Workshop   Amit Kumar N

    22  Commercial  J K Jani

    23  RSM  RSM 

  • 8/9/2019 2 Jayanti Vadoda

    8/37

    Turnaround Optimisation Program

    TR - 0

    TR - 1

    TR - 2

    TR - 3

    TR - 4

    Strategic Site TurnaroundReview

    Turnaround Work Scope

    Optimization

    Planning, Scheduling, and

    Integrated Plan Basis

    Integrated Plan Execution

    Techniques, T/A Management

    Post Turnaround Review

  • 8/9/2019 2 Jayanti Vadoda

    9/37

    .

    Turnaround Optimisation Program

    TOPTM

    Overview  Scope Cost Schedule Preparedness

    Strategic Review

    Workscope Review

    Execution Review

    Preparedness Rev.

    Close Out Review

    Ideal

    Timing

    Run Cycle (2)

    - 9 months

    - 6 months

    - 3 months

    +1 months

  • 8/9/2019 2 Jayanti Vadoda

    10/37

    Mission for Shutdown

    From Chief Turnaround Manager  

    {S R T C}

    SAFETY

    RELIABILITY

    TIME-BOUND

    COST-EFFECTIVE

  • 8/9/2019 2 Jayanti Vadoda

    11/37

    Turnaround Process / Procedure

    + Collection of all inputs such as previous reports, procurement

    lead times, job lists, own and contractor resources availabilityetc

    + Gathering information from the previous turnaround by way of

    group discussions, reviewing previous plans and turnaround

    reports

    + Finalization of job list and freezed after challenging byexperience multi disciplinary Challenging Team

    + Setting of turnaround run lengths and approximate turnaround

    duration

    + Preparation of work scope for next turnaround

    +Critical review of work scope

    + Breakdown jobs into specific activities

    + Review implementation option and resource requirement

    + Prepare an achievable plan and well integrated level I, II, III

    schedule

  • 8/9/2019 2 Jayanti Vadoda

    12/37

    Turnaround Process / Procedure

    + Procurement of material

    + Split between the jobs to be carried out by Companypersonnel and contractor

    + Contract Planning

    + Resources for running units

    + Check the jobs for pre-requisites such as scaffolding,

    insulation removal, blinds, etc+ Pre-shutdown fabrication

    + Progressive hand over of the execution portion to the field

    co-ordinators, planners, field engineers, contractor

    supervisors

    + Ensure availability of tools and construction equipment

    + Ensure adequate infrastructure facilities like, labour

    colony, canteen / space for eating for workman, medical

    facilities, transportation, drinking water, toilet facility etc… 

  • 8/9/2019 2 Jayanti Vadoda

    13/37

    Turnaround Process / Procedure

    + Administrative arrangements

    + Security arrangements

    + Implementation plans

    + Monitoring of jobs during execution

    + Contingency plan for Additional resources required

    during turnaround

    + Turnaround close-out

  • 8/9/2019 2 Jayanti Vadoda

    14/37

    Pre Shutdown Preparation

    +Keep end blinds /spectacles near line flanges as per positive isolation

    plans indicating required date for readiness on tags.

    +Keep adequate numbers of Testing Spools, temporary Connections

    for connecting pressure gauges & drains/vents for testing of Heat

    Exchangers (Both Shell & Tube side)

    +Fabrication of Spool Pieces for Heater Pigging Jobs.

    +Erection of scaffolding wherever possible e.g. For Heat Exchanger,

    inaccessible Blind locations, control Valve s, safety valves, etc.

    +Lifting and shifting arrangement for control valves , Safety Valves, etc.

    +Provision of Power supply points at planned locations e.g. laying of

    additional cable if any for welding, Hydro jetting and Hydro testing M/C.

    + Arrangement of temp. lift and Dehumidification at defined locations.

  • 8/9/2019 2 Jayanti Vadoda

    15/37

    +Detailing of Scope of work for all S/D Jobs

    +Preparation of Maintenance Execution Procedure & Work Pack for allS/D Jobs

    +Preparation of TBRA for all Critical S/D activities e.g. Hot jobs,

    Modification job, work at height or any other confined space jobs

    +Assignment of specific job responsibilities to a group of crossfunctional team e.g. team involving Maintenance, Operation, Process,

    Safety and Inspection

    +Engaging Quality & experienced contractors having good track recordof executing S/D Jobs in other Refineries to the maximum extent.

    Preparedness for Safe & Effective Execution

  • 8/9/2019 2 Jayanti Vadoda

    16/37

     

    +Inclusion of Contract Safety System in Contractor Scope

    +Arrangement for Pre S/D Training to Contract Manpower

    +Use of only Certified Tools & Tackles

    +Use of Flame Arrestor for all Vehicles,Trailors, Crane & Hydra

    +Tool Box Talk by Engineer to Contract Manpower

    +Strict Compliance of Safety Work Permit System

    +Use of General & Specific PPE’s e.g. Life line belt, Fall Arrestor  

    +Certified Lifting plan for heavy lift

    +Certification of Scaffolds & use of “Safe to use” Tag 

    Preparedness for Safe & Effective Execution

  • 8/9/2019 2 Jayanti Vadoda

    17/37

    Facilities and Services (F & S)

    1) Contractor office space / working area

     – Space for contractor’s offices have been provided in the S/D yard. Some of thecontractors will have to be located inside the units (from logistic point of view).

    2) Canteen facilities for contractor  

    SAB : Own arrangement – Space will be provided by EOL.

    ECIL : Own arrangement – Space will be provided by EOL.

    Other contractors: Tea will be served at work place as free of charge to allthe contract labour at 01.00 hr, 4.00 hrs, 7.00 hrs, 10.30

    hrs, 15.30 hrs, 16.30 hrs (incl W/s & utility)

    Two sheds are being constructed. One at shutdown yard, & another tent in oldparking area (tent by admin along with lighting. Power supply by EOL).

    Required tables, chairs, etc will be arranged by Admin.

    Lighting arrangement in tin sheds will be provided by elect dept.

    3) Canteen facilities for officers:.

    Location will be at area in between CCB & LAB.

    Tables, chairs, carpet & lighting is being organized by Admin and power supplyby electrical dept.

  • 8/9/2019 2 Jayanti Vadoda

    18/37

    Facilities and Services (F & S)

    4) Drinking Water Facilities :

    5) Shutdown office:6) Urinals & Toilets: 

    Sufficient no of toilets and urinals have been constructed in shutdown yard.

    7) Resting Place :

    Separate tents arranged for Dining and Rest room for different contract manpower as wellas for engineer. Near Shutdown yard to avoid manpower movement.  

    8) First Aid office:

    Central first aid tent will be located in front of Lab near E-W road. It will be supplemented byparamedic officer / doctor on round the clock basis and one ambulance.

    9) Accommodation for Labour / Transport.

     Accommodation for 10000 Labours have been booked in Labour colony.

    For transporting Labours from labour colony to refinery, our trailers will be used andnecessary railing arrangement is being done in our workshop for safety. In addition to thispermission will be given for walking from labour gate to workplace on the fixed route.

    10) Office space for foreign expatriates:

    11 Timing:  Working time: 08.00 to 20.00 & 20.00 to 8.00 hrs.

    Lunch time: 12.30- 13.30 hrs in two batches (30 min break)

    Dinner: 22.00 to 23.00 hrs In two batches

    Radiography timing: It will be declared on time to time & followed

  • 8/9/2019 2 Jayanti Vadoda

    19/37

    Detailed Shutdown Planning

    +Planning started with setting of Milestones for Planning activities

    +Compilation, discussion and finalization of Job list

    +Cost Estimation of S/D Jobs, Detail technical study and BOMpreparation for S/D activities, material procurement action

    +Preparation of detail scope for awarding the contract

    +Preparation of Work packs by operations and standardmaintenance procedures by maintenance

    +Finalization of resources, Heavy Equipments, Inspection Plans,identifying service requirements of technical specialist & expatriate

    +Organization of S/D meetings for review, micro detailing andfinalization of overall S/D schedule

  • 8/9/2019 2 Jayanti Vadoda

    20/37

    Turnaround Organization - September 2011Sr.

    No. Function  Name 

    1  Head-Refinery C Manoharan 2  Chief Turnaround Manager Narada Singh

    3  Overall Operation Co-Ordinator   KC Swain 

    4  Tech.Services Co-Ordinator   Satheesan V N 

    5  Construction Co-Ordinator   G G Mehta (EPIL) 

    6  HSEF  Dr Gopal Jayaraman 

    7  Turnaround manager   P Rambabu

    8  Turnaround planning Co-Ordinator   D D Chaudhari / Jayanti Vagdoda 

    9  Turnaround-MIS-Co-Ordinator   Hembala Dixit 

    10  Operation Co-Ordinator  

    ISBL: SKM Rahman

    Utility: Chitti Babu

    PIT/COT: Ajay Veer  

    11  Engineering & Inspection Ramesh Kumar  

    12  Revamp/Expansion Project Manager   Ramakrishna Paramhans (EPMCL) 

    13 Revamp/Expansion Execution

    Manager  Sudhir Porichha (EPIL) 

    14  Overall Tie-ins Co-Ordinator   Rakesh Kumar  15  Instrumentation  S. Laxminarayan 

    16  Electrical  Rajeev Kumar  

    17  Civil   Ashok Srivastava 

    18  EPS  Dhaval Doshi 

    19  Security  Cmdt. Raghuraman 

    20   Admin  Geojo Paul 

    21  Commercial  J K Jani

    22  RSM  RSM 

  • 8/9/2019 2 Jayanti Vadoda

    21/37

    + 35 days Turnaround Completed Safely ON SCHEDULE

    + Turnaround Cost within Budget as per plan. Fewvariances due to major exigencies during the Turnaround

    period.

    + Tie - ins of Train - I new units & facilities with existingrefinery : ISOM, HMU, DHDT, VGO- HT, ARU, SWS, SRU,

    DCU, & all OSBL/offsite tankages facilities

    + Revamp of existing units for capacity Augmentation hasbeen completed : CDU & VDU (18MMTPA) & consistently

    will be able to process high TAN crudes , FCCU (3.7MMTPA)& FCC operation on hydro treated feed, SRU (To Improve the

    sulphur recovery from 99 to 99.9 wt%).

    Accom pl ishments of Turnaround which w as

    completed on schedule in sp i te of lot of chal lenges  

  • 8/9/2019 2 Jayanti Vadoda

    22/37

    + Total Revamp (modification & reinstallation) completed in28 engineering days; 

    + World tallest single crude distillation column revamped (77 trays,90 meter height)

    + Vacuum distillation column revamped (4 bed, 60 meter height &new vapour horn installation)

    + Major piping modifications & replacement in existing units i.e. CDU& FCC (dismantling 75,424 inch meter & erection of 85,098 inch

    meter)

    + Revamp completed- 36 Nos. Exchangers - Modifications/Newexchangers, 7 nos. columns & 6 nos. vessels modification, 6 nos.

    new ejectors erected in VDU, 29 nos. pumps modification complete

    & boxed-up, 4 nos. Filters modification, CDU Heater A & B, VDUHeater- A & B revamp/ modifications

    Accom pl ishments of Turnaround which w as

    completed on schedule in sp i te of lot of chal lenges  

  • 8/9/2019 2 Jayanti Vadoda

    23/37

    Turnaround Key Achievement/Highlights

    + FCCU all revamp job completed within schedule without any

    incident, this includes Reactor-Riser 2 nos additional Feed

    nozzle installation, Tie Ins Job 141 nos , Additional Exchanger

    installation 2 nos along with piping, 6 nos Vessels & 4 nos

    Pumps modification

    + All Major M & I Job completed within 21 days duration, 36Column, DHDS reactor catalyst replacement, CCR/NHT Reactorcatalyst replacement, FCCU- 6 nos. bellows replacement, Flue

    gas boiler tube banks replacement, MAB Surface condenser

    replacement, SRU MCC-1 & 2 major refractory repair, UCT & PCT

    10 nos. pumps discharge line replacement, 236 Exchangers, 199Vessels, All 6 heaters pigging, 16 Heaters maintenance, 102

    PCNs (GRM & Reliability related schemes), PCN-Total INCH DIA

    :28624,Total INCH MTR: 32500,Steel Structure: 103MT

  • 8/9/2019 2 Jayanti Vadoda

    24/37

    Turnaround Key Achievement/Highlights

    + 52 Fin fan coolers, Major overhauling of over 50 Compressor/

    Turbine/ Pumps. Overhauling of 297 control valves and 551pressure safety valves,

    + DCS/ESD up gradation in all the units,

    + Capital overhauling of 145 motors, 14 Power Transformers, 45

    VACUUM circuit Breakers (33 kV), 201 Vacuum circuit Breakers

    (6.6Kv) 198 LT Circuit Breakers. 108 obsolete relays replacedwith High speed Numerical relays,

    + Bus bar differential protection scheme commissioned at Utility,

    CCR, FCCU and CDU Electrical Substations, New 33kV

    switchboard and 6.6 KV switchboard commissioned in CDU

    and Utility Substations.

    + Implementation of Fast Bus Transfer scheme at CDU, CCR,

    FCCU, DHDS, and Utility substations and many other important jobs 

  • 8/9/2019 2 Jayanti Vadoda

    25/37

  • 8/9/2019 2 Jayanti Vadoda

    26/37

    Turnaround Key Learning

    • Dehumidification system provided in CDU & VDU column was

    very effective for maintaining comfortable atmosphere insidecolumn for workmen, by maintaining temperature between 28

    to 32 deg C & Relative humidity was less than 65% inside the

    columns. This facility has remarkably contributed in reducing

    the time mainly for huge quantum of welding / hot work inside

    the column. Dehum idi f icat ion System in CDU & VDU columnDehum idi f icat ion System fo r Reactor-Riser

  • 8/9/2019 2 Jayanti Vadoda

    27/37

    Turnaround Key Learning

    • New idea of Exchanger cleaning bay has resulted in huge time

    saving by providing central Point for Cleaning of all TubeBundles with advance Hydro jetting machines i.e.

    Inside/Outside Robotic machines and Inspection (Visual &

    Eddy Current Testing) was also carried out at same place which

    helped in good housekeeping and keeping ISBL unit free from

    Oil, Coking & Sludge and Further reduced House Keeping Jobalso.

    Exchanger Cleaning Bay 

  • 8/9/2019 2 Jayanti Vadoda

    28/37

  • 8/9/2019 2 Jayanti Vadoda

    29/37

    What made it happen(from 45 to 35 Days

    •Decisive Leadership and on spot decisions.

    •Micro level Turnaround planning started well in advance before 18 months for

    man, material , machines, job list and its work pack.

    • Defined all critical jobs :

    1. CDU/VDU column Revamping.

    a. We treat contract manpower as our employee and provide all the facilities

    like Accommodations/Food/Transport/Medical/Water/Tea-Snacks at site

    only.

    b. Use of new concepts and modernized gadgets e.g. providing lifts as high

    as 90 Meters, Dehumidification /AC, Chemical decontamination etc.

    c. Maximizing the pre turnaround activities e.g. 90% scaffolding, issuing of100% bulk material/ spares and its prefabrication/ machining and placing

    in position.

    d. Daily Review and making rolling plan for speedy execution.

    e. Timely supply of equipment and logistics arrangements

  • 8/9/2019 2 Jayanti Vadoda

    30/37

    What made it happen(from 45 to 35 Days)

    2. CDU/VDU Heater Modification.

    a. Optimise the use of Pigging machines in such a way that critical Heater

    handed over with in minimum possible durations.

    b. Use of new concepts and modernized gadgets e.g.SAF RAD

    Radiographic machines so that other jobs can be continued.

    c. Heater jobs divided in multiple zones so that welding jobs can beperformed at maximum locations at a time and saved lot of time.

    d. Keep standby manpower for critical activities so that job shuld not suffer

    at any cost.

    3. FCCU Reactor Refractory repairing:

    a. Providing of Dehumidification /AC.b. Using SAF RAD Radiographic machines,Diamond cutter for refractory,

    electrical and instrument testing equipment etc.

    c. Using of skilled manpower and guidance from Refractory experts.

    d. Ensures Support services like inspection/process availability 24X7 on the

     job. 

  • 8/9/2019 2 Jayanti Vadoda

    31/37

    What made it happen(from 45 to 35 Days)

    •Decisive Leadership and on spot decisions.

    •Micro level Turnaround planning started well in advance before 18 months forman, material , machines, job list and its work pack.

    • Defined all critical jobs :

    1. CDU/VDU column Revamping.

    a. We treat contract manpower as our employee and provide all the facilities

    like Accommodations/Food/Transport/Medical/Water/Tea-Snacks at site

    only.b. Use of new concepts and modernized gadgets e.g. providing lifts as high

    as 90 Meters, Dehumidification /AC, Chemical decontamination,

    Inside/Outside Robotic Hydro jetting, SAF RAD Radiographic machines,

    powered torqueing/tensioning machines, Diamond cutter for refractory,

    Ultra-modern rotary laser based condition monitoring, electrical and

    instrument testing equipment etc.c. Maximizing the pre turnaround activities e.g. 90% scaffolding, issuing of

    100% bulk material/ spares and its prefabrication/ machining and placing

    in position.

    d. Timely supply of equipment and logistics arrangements

  • 8/9/2019 2 Jayanti Vadoda

    32/37

    •Engaged best contractor and resources and skilled/ specialized man

    power. Optimum deployment & effective utilization of resources

    •Organization of Turnaround meetings for review, micro detailing and

    finalization of overall Turnaround schedule.

    •Compliance of Systems and Procedures, Strong belief in team work,motivation and support from Top Management.

    •Caring of the Employees and Workmen resulted in excellent overall

    productivity.

    •All disciplines viz- Maintenance, Operation, TS/Process, Inspection,

    Expansion, HSEF, Security, Project/Engg, HR, CRG, IT, Warehouse,

    Commercial, Finance and Administration have demonstrated tireless

    effort and cohesive work culture towards achieving Turnaround goal.

    What made it happen(from 45 to 35 Days)

  • 8/9/2019 2 Jayanti Vadoda

    33/37

  • 8/9/2019 2 Jayanti Vadoda

    34/37

  • 8/9/2019 2 Jayanti Vadoda

    35/37

    Turnaround Sep’11 Cost : Budget Vs Actual 

    Sr.No.

    Description

    Budget-

    Material

    cost

    Budget-

    Service

    cost

    Total

    Budget (

    Material+

    Service)

    cost

    Actual

    MaterialCost

    Actual

    Service

    s Cost

    Total (Actual)

    Justification

    AMechanical/Operations (Sub

    total)15.86 40.10 55.96 18.49 35.79 54.63

    B Electrical 2.52 2.22 4.74 2.01 1.90 3.91

    C Instrument 2.99 0.99 3.98 1.64 1.26 2.90

    D Civil 0.50 2.99 3.49 1.70 5.58 7.27

    Additional Job of Sea water intakewell inside painting, Repairingand Chemical resisting coating in

    pump house basin of Sea water

    supply reservoir, CDU /VDU

    heater main flue gas duct to stackcleaning & inspection, Insulation,

    Scaffolding

    E Inspection 1.80 1.80 0.00 1.53 1.53

    F Fire & Safety 0.30 0.35 0.65 0.37 0.18 0.55

    G Admin & Canteen facilities,Vehicles, OHC & IT

    0.00 1.51 1.51 0.09 2.34 2.43

    HMaintenance

    supervisor/Engineers hiring0.00 2.53 2.53 0.00 1.47 1.47

    Total shutdown Budget (in

    crores). (Addition of A to H) 22.17 52.48 74.66 24.30 50.04 74.69

    TOTAL COST (Rs in Cr.) 74.66 73.96

    Rs in Cr.

  • 8/9/2019 2 Jayanti Vadoda

    36/37

    Turnaround Duration Schedule Vs Actual

    UNIT 

    PLANNED

    STOPPAGE DATE

    & TIME 

    ACTUAL FEED

    CUT OFF

    STOPPAGE DATE

    & TIME 

    PLANNED START-

    UP DATE & TIME 

    ACTUAL FEED

    CUT IN START UP

    DATE & TIME 

    CDU/VDU/SGU 

    18/09/11 & 08:00 hrs  18/09/11 & 04:45 hrs  23/10/11 & 08:00 hrs  24/10/11 & 11:08 hrs 

    VBU  19/09/11 & 02:00 hrs  19/09/11 & 00:30 hrs  24/10/11 & 08:00 hrs  24/10/11 & 19:15 hrs 

    TREATERS  20/09/11 & 08:00 hrs  19/09/11 & 00:30 hrs  23/10/11 & 08:00 hrs  23/10/11 & 18:00 hrs 

    FCCU  19/09/11 & 08:00 hrs  19/09/11 & 09:10 hrs  23/10/11 & 08:00 hrs  23/10/11 & 10:25 hrs 

    NHT  18/09/11 & 20:00 hrs  18/09/11 & 21:15 hrs  22/10/11 & 08:00 hrs  23/10/11 & 16:35 hrs 

    CCR  18/09/11 & 20:00 hrs  18/09/11 & 21:35 hrs  21/10/11 & 08:00 hrs  27/10/11 & 05:25 hrs 

    DHDS  18/09/11 & 20:00 hrs  18/09/11 & 20:00 hrs  24/10/11 & 08:00 hrs  29/10/11 & 16.00 hrs 

    ARU  21/09/11 & 08:00 hrs  19/09/11 & 09:00 hrs  23/10/11 & 08:00 hrs  23/10/11 & 21:00 hrs 

    SWS  21/09/11 & 12:00 hrs  21/09/11 & 08:15 hrs  23/10/11 & 08:00 hrs  24/10/11 & 04:00 hrs 

    SRU train-1  20/09/11 & 08:00 hrs  19/09/11 & 06:45 hrs  23/10/11 & 08:00 hrs  28/10/11 & 19:10 hrs 

    SRU train-2  20/09/11 & 08:00 hrs  18/09/11 & 09:00 hrs  23/10/11 & 08:00 hrs  31/10/11 & 12:00 hrs 

    UTILITY-

    UCT 29/09/11 & 08:00 hrs  27/09/11 & 17:00 hrs  11/10/11 & 08:00 hrs  13/10/11 & 16:00 hrs 

    UTILITY-

    PCT 26/09/11 & 08:00 hrs  25/09/11 & 00:00 hrs  13/10/11 & 08:00 hrs  15/10/11 & 10:00 hrs 

    H2S Flare  26/09/11 & 08:00 hrs  26/09/11 & 11:30 hrs  14/10/11 & 08:00 hrs  15.10.11 & 18.45 Hrs 

    HC Flare  30/09/11 & 08:00 hrs  26/09/11 &11:30 hrs  15/10/11 & 08:00 hrs  12/10/11 & 20:30 hrs 

    N2 Plant  01/10/11 & 08:00 hrs  06/10/11 &18:00 hrs  05/10/11 & 08:00 hrs  15/10/11 & 06:00 hrs 

    Steam  01/10/11 & 08:00 hrs  04/10/11 &08:30 hrs  05/10/11 & 08:00 hrs  10/10/11 & 09:00 hrs 

  • 8/9/2019 2 Jayanti Vadoda

    37/37