INTERNSHIP REPORT ON
STRENGTHNING OF KING EDWARD
MEDICAL UNIVERSITY, LAHORE.
A practical training report on STRENGTHNING OF KING EDWARD
MEDICAL UNIVERSITY, LAHORE from 29 July 2013 to 14 September
2013
Submitted by
Zohaid Ali
BSCE-01103123
Department of Civil Engineering
THE UNIVERSITY OF LAHORE
-
8/13/2019 Zohaid Ali
2/18
2 | P a g e
Table of ContentsIntroduction of Project ............................................................................................................................ 5
INTRODUCTION ................................................................................................................................... 5
GENERAL INFORMATION ........................................................................................................................ 6
Company Profile .................................................................................................................................. 7
Some Major Projects of the company ............................................................................................ 7
Current Project ................................................................................................................................ 7
Competency Profile ......................................................................................................................... 7
Scope of Project ...................................................................................................................................... 8
Physical Progress of the Project .......................................................................................................... 8
MATERIALS ............................................................................................................................................ 10
Steel bars........................................................................................................................................... 10
Sand................................................................................................................................................... 10
Binder materials ................................................................................................................................ 10
Water ................................................................................................................................................ 10
Equipments ........................................................................................................................................... 11
vibrator.................................................................................................Error! Bookmark not defined.
Cylinders and cubes .......................................................................................................................... 11
Concrete mixer .................................................................................................................................. 12
Concrete lifter ................................................................................................................................... 12
Instruments to install the steel cabins .............................................................................................. 12
Wheel barrows .................................................................................................................................. 13
Shuttering and Frame work .............................................................................................................. 13
Water Tanks ...................................................................................................................................... 13
Construction Management ................................................................................................................... 13
Basic Concept .................................................................................................................................... 13Selection usage of technology & method ......................................................................................... 14
Work task .......................................................................................................................................... 14
Relationship among different work activities ................................................................................... 14
Estimation of duration of work activities. ......................................................................................... 14
Requirements of resources ............................................................................................................... 14
Safety ................................................................................................................................................ 15
Dome ..................................................................................................................................................... 16
Conclusions ........................................................................................................................................... 18
-
8/13/2019 Zohaid Ali
3/18
3 | P a g e
ABSTRACT
This report is submitted for the requirements of the degree of Bachelor of
Science in civil engineering.
This report is a summer internship report submitted in partial fulfillment of the
requirements for the degree of Bachelor of Science in civil engineering as per
norms of the University of Lahore.
I visited the site for construction of King Edward medical university, Lahore in
my training period and attained technical knowledge during the project. Andafter that i was able to compile this report.
The report consists of brief study and description of material, equipments and
procedures used at site for construction of King Edward medical university.
I have put my best to elaborate the actual site conditions, the problems faced
there and the tactics used to tackle those problems.
The main objective of this report is to tell about the execution for constructionof King Edward medical university. The report also covers the basic aspects of
safety, planning, feasibility and economy at the construction site.
-
8/13/2019 Zohaid Ali
4/18
4 | P a g e
ACKNOWLEDGMENTI would like to thank prof. Zulfiqar Ali Khan HOD of civil engineering
department for permitting me to carry out this training.
I would also like to thank Mr. Basit sultan (Site engineer at the project) for
providing me the guidance and teaching me the methodologies to carry out
construction in the most efficient manner.
Finally but importantly, I would like to express my heartiest thanks to my
parents for their blessings, my friends/classmates for their help and wishes for
the successful completion of this training.
-
8/13/2019 Zohaid Ali
5/18
5 | P a g e
Introduction of Project
INTRODUCTION
Tender Documents prepared by the Consultants were issued to pre-qualified
contractors. These were received and opened by the Committee in office of the
Project Director (KEMU), Lahore on 22.06.2010. After detail scrutiny and
recommendation by the Consultants the work was awarded to lowest bidder i.e. M/s.
Progressive International, Lahore on 26.06.2010.
-
8/13/2019 Zohaid Ali
6/18
6 | P a g e
GENERAL INFORMATION
Project Strengthening of King Edward Medical
University, Lahore
Location Patiala Block, Lahore
Plot Area 7 Kanal
Covered Area 89,511 Sft.
Date of Start 1stJune, 2011
Date of Completion Two yearsJune 2013
Contract Value Rs. 228,621,989/-
Owner King Edward Medical University, Lahore.
Consultants Pakistan Environmental Planning &
Architectural Consultants (Private) Limited,Islamabad (PEPAC)
Top Supervision Project Director, King Edward Medical
University, Lahore.
Contractor M/s. Progressive International, Lahore.
-
8/13/2019 Zohaid Ali
7/18
7 | P a g e
Company Profile
This construction firm named as Hafiz Akhter was established in august 1997,
and it is the construction firms of Pakistan.
Name of the owner of the company is Mr. Hafiz Akhtar running this company.
Some Major Projects of the company
Construction of GILLANI LAW COLLEGE MULTAN. Construction of Highway.
Current Project
Construction of new block in King Edward medical university.Competency Profile
This construction firm is categorized as A class contractors in the PECrankings.
Company has more than 170 dumpers in working condition. Company has hired permanent skilled labor. Maintenance of the machineries is very good. Company has covered many mega projects all across PAKISTAN. Company plays a major role in providing job opportunities all over
PAKISTAN. And that is a very positive sign for PAKISTAN.
Company has a very vast experience in the construction of roads. Company is having very experienced skilled staff which is a good asset
for the company, and it has increased its reputation a lot.
-
8/13/2019 Zohaid Ali
8/18
8 | P a g e
Scope of Project
Construction of new block in King Edward medical university. Construction Auditorium. Class rooms. Construction of Office Rooms and Canteen. Construction of basement for car parking. Provision of Street Lights. Provision of Tuff Tiles in Parking and Shopping Areas. Total Cost Rs. 228,621,989/- Time for Completion of work of completion in 2 years. Executing Agency: Works & Services Dept. king Edward medical
university.
Physical Progress of the Project
Up to 4thfloor of building completed. Basement and auditorium completed. Temporary offices completed. 4thslab and 5thfloor were in progress. Finishing of auditorium completed. Steels are laded by workers. Concrete pouring to be made. Dome were in progress
-
8/13/2019 Zohaid Ali
9/18
9 | P a g e
Figure showing pouring of concrete and steel in 4thslab.
-
8/13/2019 Zohaid Ali
10/18
10 | P a g e
MATERIALS
Steel bars
Steel bars are laded in 8in thick slab
Sand
Sand was used to make cement paste which was used for construction.
Binder materials
These materials were used as a binder material such as cement and
concrete.
Water
Water is used to make a paste of cement and sand. And it is also used
to make concrete. It is very necessary to maintain the required strength
of concrete and to control the hydration of concrete. It is a major
component to improve workability.
-
8/13/2019 Zohaid Ali
11/18
11 | P a g e
Equipments
Vibrator
Vibrator were used for removing of air from concrete.
Cylinders and cubes
These are used for compression test of concrete before pouring infield.
-
8/13/2019 Zohaid Ali
12/18
12 | P a g e
Concrete mixer
Mixing of concrete were done by concrete mixer.
Concrete lifter
After mixing of concrete lifter were used to lift the concrete up to top
Instruments to install the steel cabins
These instruments were used to install and fix the steel cabins at site.
-
8/13/2019 Zohaid Ali
13/18
13 | P a g e
Wheel barrows
Shuttering and Frame work
Shuttering and frame work was used to construct the buildings of
beams, columns and slab.
Water Tanks
Water tanks were there to store and use water.
Construction Management
Basic Concept
Construction planning is a fundamental and challenging activity in the
management and execution of construction projects. It involves the
choice of technology, the definition of work tasks and many other
things. An effective construction plan is the base for the development
-
8/13/2019 Zohaid Ali
14/18
-
8/13/2019 Zohaid Ali
15/18
15 | P a g e
Safety
Following safety measures should be carried out on the construction
site.
There should be hard hats on site. There should be eye protection on site. There should be hearing protection near loud equipment. There should be safety shoes for workers. There should be proper first aid at the site.
-
8/13/2019 Zohaid Ali
16/18
16 | P a g e
Dome
At that time construction of dome was in progress. All the details of dome
are given
-
8/13/2019 Zohaid Ali
17/18
17 | P a g e
-
8/13/2019 Zohaid Ali
18/18
18 | P a g e
Conclusions
I worked there and I felt that my working abilities and my skill level has
improved and groomed a lot and that is a very positive sign for me. I gained the
experience to study keeping in mind the actual field so that I can implement my
knowledge in a very effective way in the field.
Main deficiency in the project was proper planning and planning lacks in almost
all the projects all over the PAKISTAN. And that causes major delays in the
duration of the projects. And safety measurements very also not taken very
effectively, and that can cause a permanent disability or a life of any person, and
that can be very shameful.
This experience was very helpful for me and I gained much more knowledge
through it. I understood the working process in the actual field and I came to
know the actual relationship between contractor, client and consultant. I felt that
actual working in the field was a bit different from studies. I observed proper
application of knowledge which I gained during studies in the field and I was
very happy after seeing that.
I also got experience in slabs and beams designing. Many of the slab and beam
were design by engineer. I saw different section of beams in which steel bars
were laid at both sides. Stirrups were provided. 8 inch thick slab were designed.The most I got experience is about domes. At that time dome construction were
in process. Which was placed on the beam. All load of dome was transferred to
beams. No such load was placed on slab of dome.
I personally think that there should be a full semester in which student can get
exposure of the field. And there should be proper grading for that so that each
and every student can pay full attention in the field work. I gained so much
experience in just one moth thats why I think that a full semester would be very
helpful for that purpose. I obtained very much experience of public dealing. I
learnt that how to deal with a labor and a higher authority person. I learnt so
many thing s which would be very helpful in my future and my career.
Major change in me that my understanding was improved a lot. And my
coordination was also groomed to another level.