ced46(8064)_24112015

Upload: vaishnavi-jayakumar

Post on 01-Mar-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 CED46(8064)_24112015

    1/218

    MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG, NEW DELHI 110002Phone: + 91 11 23230131, 23233375, 23239402 Extn 4402; Fax: + 91 11 23235529

    : 46/-3 242015

    : , 46

    .................................................................................................................................................................

    :

    1

    2 , 46

    , ,

    46:P1 3

    /,

    :

    46(8064)WC : 3

    [SP7(3) ]

    :24

    2015

    - [email protected]

    www.bis.org.in

    ,

    0

    (.. )

    : ( )

  • 7/25/2019 CED46(8064)_24112015

    2/218

    MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG, NEW DELHI 110002Phone: + 91 11 23230131, 23233375, 23239402 Extn 4402; Fax: + 91 11 23235529

    DOCUMENT DESPATCH ADVICE

    TECHNICAL COMMITTEE:

    NATIONAL BUILDING CODE SECTIONAL COMMITTEE, CED 46

    ADDRESSED TO:

    1. All Members of Civil Engineering Division Council, CEDC

    2. All Members of National Building Code Sectional Committee, CED 46 andits Panel for Administration, Development Control Rules and GeneralBuilding Requirements, CED 46:P1

    3. All other interests.

    Dear Sir/Madam,

    Please find enclosed the following draft:

    Doc. No. Title

    CED 46 (8064)WC Draft National Building Code of India: Part 3 Development Control Rulesand General Building Requirements [Thi rd Revis iono fSP 7(Part 3)]

    Kindly examine the draft and forward your views stating any difficulties which you are likely to

    experience in your business or profession if this is finally adopted as part of the National Building Code ofIndia.

    Last Date for comments: 24 December 2015 .

    Comments if any, may please be made in the format as attached, and mailed to the undersignedat the above address. You are requested to send your comments preferably through e-mail [email protected].

    In case no comments are received or comments received are of editorial nature, you may kindlypermit us to presume your approval for the above document as finalized. However, in case of commentsof technical nature are received then it may be finalized either in consultation with the Chairman,Sectional Committee or referred to the Sectional Committee for further necessary action if so desired bythe Chairman, Sectional Committee.

    This document is also hosted on BIS website www.bis.org.in.

    Thanking you,Yours faithfully,

    Sd/-

    (B. K. Sinha)Head (Civil Engg)

    Encl: as above

    DRAFT IN WIDE CIRCULATION

    Reference Date

    CED 46/T-3 24 November 2015

  • 7/25/2019 CED46(8064)_24112015

    3/218

    FORMAT FOR SENDING COMMENTS ON THE DOCUMENT

    [Please use A4 size sheet of paper only and type within fields indicated. Comments on each clause/sub-clause/ table/figure, etc, be stated on a fresh row. Information/comments should include reasons forcomments, technical references and suggestions for modified wordings of the clause. Commentsthrough e-mail in MS WORD format [email protected] shall be appreciated.]

    Doc. No.: CED 46(8064)WC BIS Letter Ref: CED 46/T-3 Dated: 24 November 2015

    Title:Draft National Building Code of India: Part 3 Development Control Rulesand General Building Requirements[Third RevisionofSP 7(Part 3)]

    Name of the Commentator/ Organization: ______________________________________

    Clause No. withPara No. or

    Table No. orFigure No.commented

    (as applicable)

    Comments / Modified Wordings Justification of Proposed Change

    mailto:[email protected]:[email protected]
  • 7/25/2019 CED46(8064)_24112015

    4/218

    Doc: CED 46 (8064)WCNovember 2015

    4

    DraftNATIONAL BUILDING CODE OF INDIAPART 3 DEVELOPMENT CONTROL RULES AND

    GENERAL BUILDING REQUIREMENTS

    [Third RevisionofSP 7(Part 3)]

    BUREAU OF INDIAN STANDARDS

  • 7/25/2019 CED46(8064)_24112015

    5/218

    Doc: CED 46 (8064)WCNovember 2015

    5

    C O N T E N T S

    FOREWORD

    1 SCOPE

    2 TERMINOLOGY

    3 LAND USE CLASSIFICATION AND USES PERMITTED

    4 MEANS OF ACCESS

    5 COMMUNITY OPEN SPACES AND AMENITIES

    6 REQUIREMENTS OF PLOTS

    7 CLASSIFICATION OF BUILDINGS

    8 OPEN SPACES (WITHIN A PLOT)

    9 AREA AND HEIGHT LIMITATIONS

    10 OFF-STREET PARKING SPACES

    11 GREENBELTS, LANDSCAPING AND WATER CONSERVATION

    12 REQUIREMENTS OF PARTS OR BUILDINGS

    13 REQUIREMENTS FOR PLANNING OF PUBLIC BUILDINGS AND SITESAS ACCESSIBLE AND BARRIER FREE FOR ELDERS AND PERSONSWITH DISABILITIES

    14 SPECIAL REQUIREMENTS OF LOW INCOME HOUSING

    15 SPECIAL REQUIREMENTS FOR CLUSTER PLANNING FOR HOUSING

    16 SPECIAL REQUIREMENTS FOR LOW INCOME HABITAT PLANNING INRURAL AREAS

    17 SPECIAL REQUIREMENTS FOR DEVELOPMENT PLANNING IN HILLYAREAS

    18 FIRE AND LIFE SAFETY

    19 DESIGN AND CONSTRUCTION

    20 LIGHTING AND VENTILATION

  • 7/25/2019 CED46(8064)_24112015

    6/218

    Doc: CED 46 (8064)WCNovember 2015

    6

    21 ELECTRICAL AND ALLIED INSTALLATIONS (INCLUDING LIGHTNINGPROTECTION OF BUILDINGS AND SOLAR ENERGY UTILIZATION)

    22 AIR CONDITIONING, HEATING AND MECHANICAL VENTILATION

    23 ACOUSTICS, SOUND INSULATION AND NOISE CONTROL

    24 HEAT INSULATION

    25 INSTALLATION OF LIFTS, ESCALATORS AND MOVING WALKS

    26 INFORMATION AND COMMUNICATION ENABLED INSTALLATIONS

    27 PLUMBING SERVICES AND SOLID WASTE MANAGEMENT

    28 SUSTAINABILITY

    29 ASSET AND FACILITY MANAGEMENT

    30 MITIGATION OF EFFECTS OF ELECTRO MAGNETIC RADIATION(EMR) IN BUILDINGS AND BUILT SPACES

    ANNEX A OFF-STREET PARKING SPACES

    ANNEX B ANTHROPOMETRICS AND SPECIFIC REQUIREMENTS FORBARRIER FREE BUILDINGS AND BUILT ENVIRONMENT

    ANNEX C SPECIAL REQUIREMENTS FOR LOW INCOMEHOUSING IN URBAN AREAS

    ANNEX D SPECIAL REQUIREMENTS OF CLUSTER PLANNINGFOR HOUSING

    ANNEX E SPECIAL REQUIREMENTS FOR LOW INCOME HABITATPLANNING IN RURAL AREAS

    ANNEX F SPECIAL REQUIREMENTS FOR DEVELOPMENTPLANNING IN HILLY AREAS

    LIST OF STANDARDS

  • 7/25/2019 CED46(8064)_24112015

    7/218

    Doc: CED 46 (8064)WCNovember 2015

    7

    IMPORTANT EXPLANTORY NOTE FOR USERS OF THE CODE

    In this Part/Section of the Code, where reference is made to good practice in relation todesign, constructional procedures or other related information, and where reference is madeto accepted standard in relation to material specification, testing, or other related information,the Indian Standards listed at the end of this Part/Section may be used as a guide to theinterpretation.

    At the time of publication, the editions indicated in the standards were valid. All standards aresubject to revision and parties to agreements based on this Part/Section are encouraged toinvestigate the possibility of applying the most recent editions of the standards.

    In the list of standards given at the end of this Section, the number appearing in the firstcolumn indicates the number of the reference in this Section. For example:

    a) Accepted standard [3(1)] refers to the Indian Standards given at serial number (1) ofthe above list given at the end of this Part 3, that is, IS 3861:2002 Method ofmeasurement of plinth, carpet and rentable areas of buildings (second revision)'.

    b) Good practice [3(2)] refers to the Indian Standard given at serial number (2) of theabove list given at the end of this Part 3, that is, IS 4878:1986 'Byelaws forconstruction of cinema buildings (first revision)'.

  • 7/25/2019 CED46(8064)_24112015

    8/218

    Doc: CED 46 (8064)WCNovember 2015

    8

    BUREAU OF INDIAN STANDARDS

    DRAFT FOR COMMENTS ONLY

    (Not to be reproduced without the permission of BIS or used as a Part of National Building Code of India)

    DraftNATIONAL BUILDING CODE OF INDIAPART 3 DEVELOPMENT CONTROL RULES AND

    GENERAL BUILDING REQUIREMENTS[Third RevisionofSP 7(Part 3)]

    ICS: 01.120; 91.040.01

    National Building Code Last Date for Comments:Sectional Committee, CED 46 24 December 2015

    National Building Code Sectional Committee, CED 46

    FOREWORD

    This Part covers development control rules, including such aspects as subdivision andlayout rules, land use classifications, open spaces, area and height limitations, means ofaccess, and parking spaces; this Part also covers the general building requirements,such as the requirements of parts of buildings, provision of lifts, etc.

    It is expected that for proper coordination and enforcement of the development control

    rules and general building requirements, the departments concerned, namely, the townand country planning department, urban development authority, urban local body andthe building department, will coordinate the total development and building activity atboth organizational and technical levels.

    Particular attention is invited to Table 5 on floor area ratio (FAR) limitations. It isemphasized that the floor area of a single storey building is limited in absolute terms bythe type of construction and occupancy class. Also, the absolute floor areas for differenttypes of construction and different occupancies have a definite ratio among them. Theratios as recommended in the American Iron and Steel Institute Publication of 1961 'Fireprotection through modern building codes' have been generally adopted in this Part and

    Table 5 has been developed on this basis. This, Table 5 is repeated in Part 4 'Fire andLife Safety' also, for convenience of reading.

    Limitation of areas and heights of buildings are regulated by specifying floor area ratio(FAR) or floor space index (FSI) and ground coverage. The significance of thecontribution of different types of construction giving different fire resistances has notbeen taken cognizance of in specifying FAR for different occupancies, in the presentdevelopment control rules and municipal byelaws of the country. Table 5, therefore,gives the comparative ratios of FAR between types of buildings and occupancy classesand these have been specified mainly from the fire protection aspect of buildings. To

  • 7/25/2019 CED46(8064)_24112015

    9/218

    Doc: CED 46 (8064)WCNovember 2015

    9

    arrive at the actual FAR for different buildings coming up in different areas, the Authorityshould further modify them, by taking into consideration other aspects like populationdensity of any area, parking facilities required, the traffic load (road width) and theservices available. The heights of buildings shall also be regulated, keeping in view thelocal fire fighting facilities.

    In some state byelaws, the FAR (or FSI) has been expressed in the form of percentage.However, the Sectional Committee responsible for preparation of this Code is of theopinion that, it being a ratio should be expressed only in the form of a ratio, as done inthis Part.

    It is particularly to be borne in mind by the Authority that the ratios are definitive and itmay assess the particular FAR for a type of construction and for an occupancy andestablish a new table, but retaining the comparative ratios as given in Table 5.

    Keeping in view the enormous problems faced by the country with regard to the everincreasing squatter settlements/pavement dwellers in urban areas (cities of all sizes), itis imperative that all the urban local bodies and urban development authorities sooneror later evolve schemes for their rehabilitation. The resources are meagre and theproblems are enormous. There has been a tendency on the part of a number of urbandevelopment authorities/urban local bodies to link space norms with affordability.

    Affordability is an important criterion but at the same time a public agency may notignore the basic minimum needs of the family to be housed (including the mental,physical and social health of the marginalized groups, which is linked with shelter). Theurban local bodies shall have to evolve appropriate policies for their integration with theoverall development process and generate/allocate resources and more importantlyadopt a planning process, which are people friendly and inclusive. The Government ofIndia has also formulated the National Rehabilitation and Resettlement Policy in 2007 to

    this effect. Therefore, keeping in view the needs of low income housing, to cater toEconomically Weaker Sections of Society (EWS) and Low Income Group (LIG), therequirements on planning, design of layout/shelter have been rationalized and the sameare provided in this Part. This will contribute significantly in the massive housingprogrammes including the Housing for All Scheme undertaken by Ministry of UrbanDevelopment for the low income sector. This information is based on the provisions ofIS 8888 (Part 1):1993 'Guide for requirements of low income housing: Part 1 Urbanareas (first revision).

    Further, city development process would need a dynamic approach to take care of urbanrenewal and also development needs in dense core areas of the cities. Innovative

    approaches in planning and design with participatory models of public private-peoplespartnership become necessary to solve the emerging development needs. With this inview, many city development authorities have evolved innovative planning anddevelopment tools like transferable development rights (TDR) where the developerwould receive a portion of the development rights in a new location, keeping in view theconstraints in the existing land area and the development potential. Such developmentrights may be transferred into outskirts or new developed areas where land availability isassured. This would encourage the professionals and developers to participate in urbanrenewal and at the same time ensure that the developments in both the inner core areas

  • 7/25/2019 CED46(8064)_24112015

    10/218

    Doc: CED 46 (8064)WCNovember 2015

    10

    and new areas take place in a planned manner. The TDR concept should beincreasingly encouraged by the authority dealing with urban renewal, redevelopmentprojects including housing and redevelopment projects for slum dwellers.

    Urbanization in India is taking place at a rapid pace. As per the 2011 Census,31.16 percent of the countrys population resides in urban areas. This figure was 27.8percent in 2001. The urban component is expected to rise to around 40 percent by 2020.

    As Indian cities continue to grow demographically and spatially, the challenge ofimproving urban infrastructure is enormous. While the number of urban centres hasincreased manifold between 1901 and 2011, the urban population increased six fold,resulting in a top-heavy urban settlement hierarchy with a large number of primatesettlements. It is expected that the number of towns and cities which was 7 933 as perCensus, 2011 is likely to cross the 10 000 mark in next two decades. As a result ofliberalization, the demographic trends of urbanization are accompanied by bothchallenges and opportunities in the management and financing of urban development.

    Unprecedented urbanization has been fuelled by rapid economic growth andeven more rapid industrialization especially in the past three decades or so. Withglobalization, this trend of rapid economic growth and urbanization is likely to accentuatefurther. In 1901, Kolkata was the only metropolitan city (million plus) in the country. Thenumber of metropolitan cities increased to 5 in 1951, 12 in 1981, 23 in 1991, 35 in 2001and 53 in 2011. The 53 metropolitan cities together account for a population of about158 million in 2011, that is, 42 percent of urban population of the country. It is expectedthat this number would be about 85 by 2051.

    Going by the present trends, by 2051, India would be the most populous countrywith 1.70 billion people and 0.19 ha per capita land availability. By 2051, 820 millionpeople will live in urban settlements constituting about 50 percent of the total population.

    Cities in the country would emerge as centres of both hope and despair: while beingengines of economic and social development they may also be congested centres ofpoverty and environmental degradation. The million plus cities constitute 42 percent ofthe total urban population, while the Class I (more than 1 lakh population) townsconstituted 60.04 percent, followed by 11 percent in Class II (50 000-100 000population) towns,15.4 percent in Class III (20 000-50 000 population) towns and therest 13.56 percent constituted by Class IV, V and VI towns (less than 20 000population).

    Further, in the Indian practice, mega-cities (cities over 50 lakhs population) are 8in number; metro-cities (cities having 10 to 50 lakhs population) are 45 in number.

    These 53 cities above 10 lakhs population is likely to be above 70 by 2021. The othercities are either small or medium towns or cities with different population limits.Urbanization in above cities and towns (mega-cities, metro-cities, small and mediumtowns and cities) will be different in nature and the development challenges are alsodifferent keeping in view the extent of urbanization, industrialization, commercializationand the nature of transportation needs. Therefore, the Code provisions should beappropriately utilized depending upon the need of hierarchy of cities for which theadministrative and technical requirements have been covered in the Code for variousfacets of the activity.

  • 7/25/2019 CED46(8064)_24112015

    11/218

    Doc: CED 46 (8064)WCNovember 2015

    11

    The first version of this Part was prepared in 1970. As a result of incorporation of thisPart in the revised development control rules and building byelaws of some municipalcorporations and municipalities, some useful suggestions had emerged. First revision ofthis Part was brought out in 1983, where these suggestions were incorporated to theextent possible. The major modifications incorporated in the first revision included:

    a) Addition of development control rules giving guidance on means of access,community spaces and other aspects required for planning layouts.

    b) Addition of provisions regarding plot sizes and frontage for different types ofbuildings, such as detached, semi-detached, row type and special housingschemes.

    c) Requirements of open spaces for other occupancies, such as educational,institutional, assembly, industrial buildings, etc were included.

    d) Provisions relating to interior open space were elaborated, includingrequirements for ventilation shaft.

    e) Requirements of open spaces for group housing development were covered.

    f) Requirements of off-street parking spaces were covered.

    g) Requirements for greenbelts and landscaping including norms for plantationsof shrubs and trees were covered.

    h) Requirements of certain parts of buildings, such as loft, store room, garage,

    basement, chimney, parapet, cabin, boundary wall, wells, septic tanks, office-cum-letter box room, meter room were included.

    j) Special requirements of low income housing were covered.

    The term Development Control Rules used in this Part encompasses the related aspectscomprehensively with a view to promoting orderly development of an area.

    The major modifications incorporated in the second revision included :

    a) Terminology given in this Part were made exhaustive by incorporating

    definitions of additional terms used, such as access, chimney, to erect, etcand number of terms pertaining to cluster planning for housing.

    b) Detailed planning norms/open spaces for various amenities such aseducational facilities, health care facilities, socio-cultural facilities, distributionservices, police, civil defence and home guards, and fire services wereincluded.

  • 7/25/2019 CED46(8064)_24112015

    12/218

    Doc: CED 46 (8064)WCNovember 2015

    12

    c) Off-street parking requirements were also included for cities with population(i) between 1 000 000 and 5 000 000, and (ii) above 5 000 000 (seeAnnex

    A).

    d) Special requirements for low income housing were modified and updatedbased on the revision of concerned Indian Standard namely IS 8888:1978 asIS 8888(Part 1):1993 'Guide for requirements of low income housing: Part 1Urban area (first revision)'. Single room dwelling was discouraged,guidelines for water seal latrine were incorporated, and cluster planningapproach were recommended.

    e) Requirements for cluster planning for housing were added based on theguidelines given in IS 13727:1993 'Guide for requirements of cluster planningfor housing'.

    f) Special requirements for low income housing for rural habitat planning wereadded.

    g) Special requirements for development planning in hilly areas were added.

    h) The requirements for buildings and facilities for the physically challengedwere revised, with listing of additional categories of physically challenged;modifications in requirements of ramps, stairs, doors, handrails and controls;and incorporation of additional requirements regarding windows.

    In this (third) revision, following major modifications have been incorporated:

    a) Definitions of additional terms have been included and some of the existing

    definition have been modified in the terminology clause.

    b) Reference of IS 3861:2002 'Method of measurement of plinth, carpet andrentable areas of buildings (second revision) has been added for correctinterpretation of plinth area and built-up area.

    c) Land use classification has been modified.

    d) A new clause on footpaths giving guidance on width of footpath to beadopted based on expected pedestrian traffic as also recommended width offootpath corresponding to adjacent land use, has been added.

    e) Provisions on Transferable Development Rights (TDR) including types ofTDR and guidance on their usage has been included.

    f) Provisions for buildings on podium including permitted uses in podium,general requirements for the same and requirements for fire tendermovement have been incorporated under the clause on means of access.

  • 7/25/2019 CED46(8064)_24112015

    13/218

    Doc: CED 46 (8064)WCNovember 2015

    13

    g) Planning norms for amenities have been modified and new amenities havebeen covered.

    h) Requirements for minimum clearances from an overhead electric supply linehave been modified based on current Central Electricity Authority (MeasuresRelating to Safety and Electric Supply) Regulations, 2010 taking into accounteffect of sag and wind pressure.

    j) Provisions for sunken courtyard have been added for meeting the light andventilation requirements for basement area.

    k) For height restrictions in the vicinity of aerodromes, reference to concernednotification of the Ministry of Civil Aviation, Govt of India has been made.

    m) Provisions for underground or multi-storeyed parking as also mechanizedparking of vehicles has been included.

    n) Provisions have been made in the Code to consider permitting mercantileoccupancy in the first basement subject to compliance of all requirements forfire safety in accordance with Part 4 'Fire and Life Safety' and necessarymeasures for required lighting, ventilation and water supply, drainage andsanitation.

    p) Requirements for planning of buildings and sites as accessible and barrierfree for elders and persons with disabilities, have been thoroughly revisedand updated.

    q) Provisions for solar energy utilization have been included.

    r) Special requirements for low income housing have been updated.

    s) Special requirements for development planning in hilly areas have beenupdated.

    t) Guidelines for mitigation of effects of electro magnetic radiation in buildingsand built spaces have been included.

    The information contained in this section is also based on the following IndianStandards:

    IS 4963:1987 Recommendations for buildings and facilities forphysically handicapped (first revision)

    IS 8888 (Part 1):1993

    Guide for requirements of low income housing :Part 1 Urban area (first revision)

    IS 13727:1993 Guide for requirements of cluster planning forhousing

  • 7/25/2019 CED46(8064)_24112015

    14/218

    Doc: CED 46 (8064)WCNovember 2015

    14

    In revising the provisions of this Part, assistance has also been derived from thefollowing publication:

    URDPFI Guidelines, 2014,

    IRC: 103-2012 'Guidelines for Pedestrian Facilities (first revision)'

    ISO 21542:2011 Building construction Accessibility and usability of the builtenvironment

    Planning a barrier free environment, 2011 prepared by Office of the ChiefCommissioner for Persons with Disabilities, Ministry of Social Justice andEmpowerment, Government of India

    Handbook on Barrier Free and Accessibility, 2014 prepared by Central PublicWorks Department

    All standards cross-referred here or in the main text of this Part, are subject to revision.The parties to agreement based on this Part are encouraged to investigate thepossibility of applying the most recent editions of the standards.

    For the purpose of deciding whether a particular requirement of this Part of the Code iscomplied with, the final value, observed or calculated, expressing the result of a test oranalysis, shall be rounded off in accordance with IS 2:1960 'Rules for rounding off

    numerical values (revised)'. The number of significant places retained in the rounded offvalue should be the same as that of the specified value in this Part.

  • 7/25/2019 CED46(8064)_24112015

    15/218

    Doc: CED 46 (8064)WCNovember 2015

    15

    BUREAU OF INDIAN STANDARDS

    DRAFT FOR COMMENTS ONLY

    (Not to be reproduced without the permission of BIS or used as a Part of National Building Code of India)

    DraftNATIONAL BUILDING CODE OF INDIAPART 3 DEVELOPMENT CONTROL RULES AND

    GENERAL BUILDING REQUIREMENTS[Third RevisionofSP 7(Part 3)]

    ICS: 01.120; 91.040.01

    National Building Code Last Date for Comments:Sectional Committee, CED 46 24 December 2015

    1 SCOPE

    This Part deals with the development control rules and general building requirements toensure health and safety of the public.

    2 TERMINOLOGY

    2.0 For the purpose of this Part, the following definitions shall apply :

    2.1 AccessA clear approach to a plot or a building.

    2.2 Accessory Use Any use of the premises subordinate to the principal use andcustomarily incidental to the principal use.

    2.3 AlterationA change from one occupancy to another, or a structural change, suchas an addition to the area or height, or the removal of part of a building, or any change tothe structure, such as the construction of, cutting into or removal of any wall, partition,column, beam, joist, floor (including a mezzanine floor) or other support, or a change toor closing of any required means of ingress or egress or a change to the fixtures orequipment.

    2.4 ApprovedApproved by the Authority having jurisdiction.

    2.5 Authority Having JurisdictionThe Authority which has been created by a statuteand which for the purpose of administering the Code/Part may authorize a committee oran official to act on its behalf; hereinafter called the 'Authority.

    2.6 Back to Back ClusterClusters when joined back to back and/or on sides (seeFig.1).

  • 7/25/2019 CED46(8064)_24112015

    16/218

    Doc: CED 46 (8064)WCNovember 2015

    16

    2.7 Balcony A horizontal projection, with a handrail or balustrade or a parapet, toserve as passage or sitting out place.

    2.8 Basement or CellarThe lower storey of a building, below or partly below groundlevel.

    2.9 Building Any structure for whatsoever purpose and of whatsoever materialsconstructed and every part thereof, whether used as human habitation or not andincludes foundation, plinth, walls, floors, roofs, chimneys, plumbing and buildingservices, fixed platforms, VERANDAH, balcony, cornice or projection, part of a buildingor anything affixed thereto or any wall enclosing or intended to enclose any land orspace and signs and outdoor display structures. Tents, SHAMIANAHS, tarpaulinshelters, etc, erected for temporary and ceremonial occasions with the permission of the

    Authority shall not be considered as building.

    2.10 Building, Height of The vertical distance measured in the case of flat roofs,

    from the average level of the ground around and contiguous to the building or asdecided by the Authority to the terrace of last livable floor of the building adjacent to theexternal walls; and in the case of pitched roofs, up to the point where the externalsurface of the outer wall intersects the finished surface of the sloping roof; and in thecase of gables facing the road, the mid-point between the eaves level and the ridge.

    Architectural features serving no other function except that of decoration shall beexcluded for the purpose of measuring heights. See9.4.2.1.

    2.11 Building EnvelopeThe horizontal spatial limits up to which a building may bepermitted to be constructed on a plot.

    2.12 Building LineThe line up to which the plinth of a building adjoining a street oran extension of a street or on a future street may lawfully extend. It includes the linesprescribed, if any, in any scheme. The building line may change from time to time asdecided by the Authority.

    2.13 CabinA non-residential enclosure constructed of non-load bearing partition.

    2.14 CanopyA projection over any entrance.

  • 7/25/2019 CED46(8064)_24112015

    17/218

    Doc: CED 46 (8064)WCNovember 2015

    17

    2.15 Carpet AreaThe covered area of the usable rooms at any floor level (excludingthe area of the wall) {seeaccepted standard [3(1)]}.

    2.16 CHHAJJA A sloping or horizontal structural overhang usually provided overopenings on external walls to provide protection from sun and rain.

    2.17 Chimney An upright shaft containing one or more flues provided for theconveyance to the outer air of any product of combustion resulting from the operation ofheat producing appliance or equipment employing solid, liquid or gaseous fuel.

    2.18 Chowk or CourtyardA space permanently open to the sky, enclosed fully orpartially by building and may be at ground level or any other level within or adjacent to abuilding.

    2.19 Chowk, InnerA chowk enclosed on all sides.

    2.20 Chowk, OuterA chowk one of whose sides is not enclosed.

    2.21 Closed ClustersClusters with only one common entry into cluster open space(see Fig. 2).

    2.22 ClusterPlots or dwelling units or housing grouped around an open space (seeFig. 3).

    Ideally housing cluster should not be very large. In ground and one storeyed structuresnot more than 20 houses should be grouped in a cluster. Clusters with more dwelling

    units will create problems in identity, encroachments and of maintenance.

  • 7/25/2019 CED46(8064)_24112015

    18/218

    Doc: CED 46 (8064)WCNovember 2015

    18

    2.23 Cluster Court Town HouseA dwelling in a cluster plot having 100 percent ornearly 100 percent ground coverage with vertical expansion, generally limited to one

    floor only and meant for self use .

    2.24 Cluster PlotPlot in a cluster.

    2.25 Cooking Alcove A cooking space having direct access from the main roomwithout any inter-communicating door.

    2.26 Covered Area Ground area covered by the building immediately above theplinth level. The area covered by the following in the open spaces is excluded fromcovered area (see Table 4) :

    a) Garden, rockery, well and well structures, plant nursery, waterpool, swimmingpool (if uncovered), platform round a tree, tank, fountain, bench, CHABUTRAwith open top and unenclosed on sides by walls and the like;

    b) Drainage culvert, conduit, catch-pit, gully pit, chamber, gutter and the like;c) Compound wall, gate, unstoreyed porch and portico, canopy, slide, swing,

    uncovered staircase, ramps areas covered by CHHAJJA and the like; andd) Watchmens booth, pumphouse, garbage shaft, electric cabin or sub-stations,

    and such other utility structures meant for the services of the building underconsideration.

    NOTE For the purpose of this Part, covered area equals the plot area minus the areadue for open spaces.

    2.27 Cul-de-Sac Cluster

    Plots/dwelling units when located along a pedestrianized or vehicular cul-de-sac road(see Fig. 4).

  • 7/25/2019 CED46(8064)_24112015

    19/218

    Doc: CED 46 (8064)WCNovember 2015

    19

    2.28 DensityThe residential density expressed in terms of the number of dwellingunits per hectare.

    NOTE Where such densities are expressed exclusive of community facilities and provision ofopen spaces and major roads (excluding incidental open spaces), these will be net residentialdensities. Where these densities are expressed taking into consideration the required open spaceprovision and community facilities and major roads, these would be gross residential densities atneighbourhood level, sector level or town level, as the case may be. The provision of openspaces and community facilities will depend on the size of the residential community.

    Incidental open spaces are mainly open spaces required to be left around and in between twobuildings to provide lighting and ventilation.

    2.29 Detached BuildingA building detached on all sides.

    2.30 Development - `Development with grammatical variations means the carryingout of building, engineering, mining or other operations, in, or over, or under land orwater, on the making of any material change, in any building or land, or in the use of anybuilding, land, and includes redevelopment and layout and subdivision of any land; and'to develop' shall be construed accordingly.

    2.31 DrainA conduit, channel or pipe for the carriage of storm water, sewage, wastewater or other water borne wastes in a building drainage system.

    2.32 DrainageThe removal of any liquid by a system constructed for the purpose.

    2.33 Dwelling Unit/TenementAn independent housing unit with separate facilitiesfor living, cooking and sanitary requirements.

    2.34 EscalatorA power driven, inclined, continuous moving stairway used for raisingor lowering passengers.

    2.35 Exit A passage, channel or means of egress from any building, storey or floorarea to a street or other open space of safety.

    2.36 External Faces of ClusterBuilding edges facing the cluster open spaces.

  • 7/25/2019 CED46(8064)_24112015

    20/218

    Doc: CED 46 (8064)WCNovember 2015

    20

    2.37 Fire SeparationThe distance in metres measured from the external wall of thebuilding concerned to the external wall of any other building on the site, or from othersite, or from the opposite side of a street or other public space for the purpose ofpreventing the spread of fire.

    2.38 FloorThe lower surface in a storey on which one normally walks in a building.The general term floor unless specifically mentioned otherwise shall not refer to a'mezzanine floor'.

    2.39 Floor Area Ratio (FAR) The quotient obtained by dividing the total coveredarea (plinth area) on all floors by the area of the plot:

    Total covered area of all floorsFAR = ------------------------------------------

    Plot area

    2.40 GalleryAn intermediate floor or platform projecting from a wall of an auditoriumor a hall providing extra floor area, additional seating accommodation, etc. It shall alsoinclude the structures provided for seating in stadia.

    2.41 Garage, PrivateA building or a portion thereof designed and used for parkingof private owned motor driven or other vehicles.

    2.42 Garage, Public A building or portion thereof, other than a private garage,designed or used for repairing, servicing, hiring, selling or storing or parking motor drivenor other vehicles.

    2.43 Group HousingHousing for more than one dwelling unit, where land is ownedjointly (as in the case of co-operative societies or the public agencies, such as localauthorities or housing boards, etc) and the construction is undertaken by one Agency.

    2.44 Group Open SpaceOpen space within a cluster.

    Group open space is neither public open space nor private open space. Each dwellingunit around the cluster open space have a share and right of use in it. The responsibilityfor maintenance of the same is to be collectively shared by all the dwelling units around.

    2.45 Habitable RoomA room occupied or designed for occupancy by one or morepersons for study, living, sleeping, eating, kitchen if it is used as a living room, but notincluding bathrooms, water-closet compartments, laundries, serving and store pantries,corridors, cellars, attics, and spaces that are not used frequently or during extendedperiods.

    2.46 Independent Cluster Clusters surrounded from all sides by vehicular accessroads and/or pedestrian paths (seeFig. 5).

  • 7/25/2019 CED46(8064)_24112015

    21/218

    Doc: CED 46 (8064)WCNovember 2015

    21

    2.47 Interlocking Cluster Clusters when joined at back and on sides with at leastone side of a cluster common and having some dwelling units opening onto or havingaccess from the adjacent clusters.

    Dwelling units in such clusters should have at least two sides open to external openspace. Houses in an interlocking cluster may have access, ventilation and light from theadjacent cluster and should also cater for future growth (see Fig. 6).

    2.48 Internal Faces of ClusterBuilding edges facing the adjacent cluster open space(as in case of interlocking cluster) of the surrounding pedestrian paths or vehicularaccess roads.

    2.49 Ledge or TANDA shelf-like projection, supported in any manner whatsoever,except by means of vertical supports within a room itself but not having projection widerthan one metre.

    2.50 Lift An appliance designed to transport persons or materials between two ormore levels in a vertical or substantially vertical direction by means of a guided car orplatform. The word `elevator is also synonymously used for `lift.

    2.51 LoftA structure providing intermediate storage space in between two floors witha maximum height of 1.5 m, without having a permanent access.

  • 7/25/2019 CED46(8064)_24112015

    22/218

    Doc: CED 46 (8064)WCNovember 2015

    22

    2.52 Master Plan A Master Plan formulated under any relevant Act (Town andCountry Planning or Development Act or Municipal Act) for any town, approved andnotified by the State Government.

    2.53 Mezzanine FloorAn intermediate floor between two floors of any storey formingan integral part of floor below.

    2.54 Occupancy or Use GroupThe principal occupancy for which a building or a partof a building is used or intended to be used; for the purposes of classification of abuilding according to occupancy; an occupancy shall be deemed to include subsidiaryoccupancies which are contingent upon it.

    2.55 Occupancy, Mixed A multiple occupancy where the occupancies areintermingled.

    2.56 Open Clusters Clusters where cluster open spaces are linked to form acontinuous open space (seeFig. 7).

    2.57 Open SpaceAn area, forming an integral part of the plot, left open to the sky.

    NOTE The open space shall be the minimum distance measured between the front, rear andside of the building and the respective plot boundaries.

    2.58 Open Space, Front An open space across the front of a plot between thebuilding line and front boundary of the plot.

    2.59 Open Space, RearAn open space across the rear of a plot between the rear ofthe building and the rear boundary of the plot.

    2.60 Open Space, SideAn open space across the side of the plot between the sideof the building and the side boundary of the plot.

    2.61 OwnerPerson or body having a legal interest in land and/or building thereon.This includes free holders, leaseholders or those holding a sub-lease which bothbestows a legal right to occupation and gives rise to liabilities in respect of safety orbuilding condition.

  • 7/25/2019 CED46(8064)_24112015

    23/218

    Doc: CED 46 (8064)WCNovember 2015

    23

    In case of lease or sublease holders, as far as ownership with respect to the structure isconcerned, the structure of a flat or structure on a plot belongs to the allottee/lessee tillthe allotment/lease subsists.

    2.62 ParapetA low wall or railing built along the edge of a roof or floor.

    2.63 Parking SpaceAn area enclosed or unenclosed, covered or open, sufficient insize to park vehicles, together with a drive-way connecting the parking space with astreet or alley and permitting ingress and egress of the vehicles.

    2.64 Partition An interior non-load bearing barrier, one storey or part-storey inheight.

    2.65 PlinthThe portion of a structure between the surface of the surrounding groundand surface of the floor, immediately above the ground.

    2.66 Plinth Area The built up covered area measured at the floor level of thebasement or of any storey {seeaccepted standard [3(1)]}.

    2.67 PorchA covered structure supported on pillars or otherwise for the purpose ofpedestrian or vehicular approach to a building.

    2.68 RoadSeeStreet.

    2.69 Road LineSee Street Line.

    2.70 Room HeightThe vertical distance measured from the finished floor surface tothe finished ceiling surface. Where a finished ceiling is not provided, the underside of

    the joists or beams or tie beams shall determine the upper point of measurement.

    2.71 Row Housing/Row Type BuildingA row of buildings, with only front, rear andinterior open spaces, where applicable.

    2.72 Semi-Detached BuildingA building detached on three sides.

    2.73 Service Road/Lane A road/lane provided adjacent to a plot(s) for access orservice purposes as the case may be.

    2.74 Set-Back LineA line usually parallel to the plot boundaries and laid down ineach case by the Authority, beyond which nothing may be constructed towards the plotboundaries.

    2.75 Site (Plot)A parcel (piece) of land enclosed by definite boundaries.

    2.76 Site, CornerA site at the junctions of and fronting on two or more intersectingstreets.

  • 7/25/2019 CED46(8064)_24112015

    24/218

    Doc: CED 46 (8064)WCNovember 2015

    24

    2.77 Site, Depth of The mean horizontal distance between the front and rear siteboundaries.

    2.78 Site, Double FrontageA site, having a frontage on two streets, other than acorner plot.

    2.79 Site, Interior or TandemA site access to which is by a passage from a streetwhether such passage forms part of the site or not.

    2.80 Staircover (or MUMTY)A structure with a roof over a staircase and its landingbuilt to enclose only the stairs for the purpose of providing protection from weather andnot used for human habitation.

    2.81 StoreyThe portion of a building included between the surface of any floor andthe surface of the floor next above it, or if there be no floor above it, then the spacebetween any floor and the ceiling next above it.

    2.82 Storey, Topmost The uppermost storey in a building whether constructedwholly or partly on the roof.

    2.83 Street Any means of access, namely, highway, street, lane, pathway, alley,stairway, passageway, carriageway, footway, square, place or bridge, whether athoroughfare or not, over which the public have a right of passage or access or havepassed and had access uninterruptedly for a specified period, whether existing orproposed in any scheme, and includes all bunds, channels, ditches, storm-water drains,culverts, sidewalks, traffic islands, roadside trees and hedges, retaining walls, fences,barriers and railings within the street lines.

    2.84 Street Level or Grade The officially established elevation or grade of thecentral line of the street upon which a plot fronts and if there is no officially establishedgrade, the existing grade of the street at its mid-point.

    2.85 Street LineThe line defining the side limits of a street.

    2.86 To erectTo erect a building means :

    a) to erect a new building on any site whether previously built upon or not; andb) to re-erect any building of which portions above the plinth level have been pull

    down, burnt or destroyed.

    2.87 Tower-like StructuresStructures shall be deemed to be tower-like structureswhen the height of the tower-like portion is at least twice the height of the broader baseat ground level.

    2.88 VERANDAHA covered area with at least one side open to the outside with theexception of 1 m high parapet on the upper floors to be provided on the open side.

  • 7/25/2019 CED46(8064)_24112015

    25/218

    Doc: CED 46 (8064)WCNovember 2015

    25

    2.89 Volume to Plot Area Ratio (VPR)The ratio of volume of building measured incubic meters to the area of the plot measured in square meters and expressed inmetres.

    2.90 Water-Closet (WC) A water flushed plumbing fixture designed to receivehuman excrement directly from the user of the fixture. The term is used sometimes todesignate the room or compartment in which the fixture is placed.

    2.91 WindowAn opening to the outside other than a door, which provides all or partof the required natural light or ventilation or both to an interior space.

    3 LAND USE CLASSIFICATION AND USES PERMITTED

    3.1 Land Use Classification

    The land use classification may be as indicated below:

    SlNo.

    Level 1 Level 2

    N A-N Use Category N A-N Use Zone

    i) 1. R Residential 11 R-1 Primary Residential Zone

    12 R-2 Unplanned/Informal Residential Zone

    ii) 2. C Commercial 21 C-1 Retail Shopping Zone

    22 C-2 General Business and Commercial District/Centres

    23 C-3 Wholesale, Godowns, Warehousing/ RegulatedMarkets

    24 C-4 Service Sector

    25 C-5 Regulated/ Informal/ Weekly Markets

    iii) 3. I Industry 31 I-1 Service and Light Industry

    32 I-2 Extensive and Heavy Industry

    33 I-3 Special Industrial Zone - Hazardous, Noxiousand Chemical

    iv) 4. PS Public and Semi-Public

    41 PS-1 Govt./ Semi Govt./ Public Offices

    42 PS-2 Govt. Land (use undetermined)

    43 PS-3 Police Headquarter/Station, Police Line

    44 PS-4 Educational and Research

    45 PS-5 Medical and Health

    46 PS-6 Social Cultural and Religious (inc. Cremation

    and Burial Grounds)47 PS-7 Utilities and Services

    v) 5. M Mixed Use 51 M-1 Mixed Industrial use Zone

    52 M-2 Mixed Residential Zone

    53 M-3 Mixed Commercial Zone

    vi) 6. P Recreational 61 P-1 Playgrounds/Stadium/Sports Complex

    62 P-2 Parks and GardensPublic Open Spaces63 P-3 Multi-open Space (MAIDAN)

  • 7/25/2019 CED46(8064)_24112015

    26/218

    Doc: CED 46 (8064)WCNovember 2015

    26

    SlNo.

    Level 1 Level 2

    N A-N Use Category N A-N Use Zone

    vii) 7. T TransportationandCommunication

    71 T-1 Roads/Bus Rapid Transit System (BRTS)

    72 T-2 Railways/Mass Rapid Transit System (MRTS)

    73 T-3 Airport

    74 T-4 Seaports and Dockyards

    75 T-5 Bus Depots/Truck Terminals and FreightComplexes

    76 T-6 Transmission and Communication

    viii) 8. A Primary Activity 81 PA-1 Agriculture

    82 PA-2 Forest and Horticulture

    83 PA-3 Poultry and Dairy Farming

    84 PA-4 Rural Settlements

    85 PA-5 Brick Kiln and Extractive Areas

    86 PA-6 Others (Fishing, Pottery etc.)

    ix) 9. E Protective andUndevelopableUse Zone

    91 E-1 Water Bodies

    92 E-2 Special Recreation Zone/Protective Areas suchas Sanctuaries/Reserve Forests and Eco-sensitive zone

    93 E-3 Undevelopable Use Zone

    x) 10. S Special Area 101 S-1 Old Built-up (Core) Area

    102 S-2 Heritage and Conservation Areas

    103 S-3 Scenic Value Areas104 S-4 Government Restricted Area (such as Defence)

    105 S-5 Other Uses/ Spot Zone (seeNote 5)

    1)Numeric Code

    2)Alpha-numeric Code

    NOTES

    1 Overall, there could be 43 use zones at the development plan level within 10 land use categoriesat the perspective plan level as given in the above table.

    2 Areas of informal activities may be identified in the above land use categories at Level 2 for 1 to 7Level 1 Use Zones only.

    3 Mixed use zone shall be identified at the development plan level, having dominant use and mixeduse.

    4 Use permissions for different activities, as specified in the next section on simplified use zoneregulations may be provided at the project/action plan level or with the approval of the StatutoryAuthority as the case may be.

    5 The process of changing/relaxing/modifying land use of part or Spot of a zone in a particularland use is termed as Spot Zoning. Spot zoning may be done for comparatively smaller area ina particular land use zone in such a way that it does not affect the overall development plan.

    6 Use zone regulations for the use permissibility (from the suggestive list) could be decided by thetown planner depending upon the requirement/feasibility.

  • 7/25/2019 CED46(8064)_24112015

    27/218

    Doc: CED 46 (8064)WCNovember 2015

    27

    7 Appropriate code in terms of both numerical and alphabetic (letter) are provided to facilitate thereference and to have a simplified procedure to follow.

    3.2 The various building uses and occupancies (see7) permitted on the various zonesshall be as given in the Master Plan of the town/city concerned.

    3.3 Uses to be in Conformity with the Zone

    Where the use of buildings or premises is not specifically designated on theDevelopment/Master Plan or in the absence of Development Plan, shall be in conformitywith the zone in which they fall.

    3.4 Uses as Specifically Designated on Development/Master Plan

    Where the use of a site is specifically designated on the Development/Master Plan, itshall be used only for the purpose so designated.

    3.5 Non-conforming Uses

    No plot shall be put to any use, occupancy or premises other than the uses identified in3.1, except with the prior approval of the Authority.

    3.6 Fire Safety

    Buildings shall be so planned, designed and constructed as to ensure fire safety and thisshall be done as per Part 4 'Fire and Life Safety'.

    3.7 Transferable Development Rights (TDR)

    3.7.1 Transferable development rights (TDR) means making available certain amount ofadditional built up area in lieu of the area relinquished or surrendered by the owner ofthe land, so that he may use such built up area either himself or transfer it to some otherin need of the same for an agreed sum of money. The process of land acquisition inurban areas for public purpose especially for road widening, parks and play grounds,schools etc, is complicated, costly and time consuming. In order to minimize the timeneeded and to enable a process, TDR may be advantageously used to acquire land forall such purposes.

    Based on the intensity of development, the city may be divided into intensively

    developed, moderately developed and sparsely developed zones in the plan. Thetransfer of development rights shall be from intensively developed zone to other zonesand not vice versa.

    3.7.2 Types of TDR and their Usage

    For the convenience of understanding and application, the TDR may be classified intofollowing types:

  • 7/25/2019 CED46(8064)_24112015

    28/218

    Doc: CED 46 (8064)WCNovember 2015

    28

    a) General TDR - General TDR consist of TDR generated through road,reservation land and construction amenities. The owner shall handover/surrender the land which is reserved for public purpose in thedevelopment plan and where additional amenities are required. In lieu of this,he is entitled to TDR equivalent to the area of the land handed over free ofcharge to the authority.

    b) Slum TDR -Slum TDR is generated in case of redevelopment/rehabilitation ofeligible slums. It is incentive given to the developer for redevelopment ofblighted slum area. Slum TDR may be used in non-receiving zones also, if sodecided by the Authority.

    c) Heritage TDR - Heritage TDR is generated due to loss of developmentpotential under heritage building and heritage precincts. This TDR may beused in non-receiving zones of high potential areas, if so decided by the

    Authority, so as to encourage the owner to come forward for the same .

    Although TDR may be generated anywhere in the city, the usage of TDR is controlled bythe following guidelines:

    a) General TDR may be used on plots:1) In the same ward where it is generated, or at the remaining area of the

    originating plot, and2) It shall be allowed to be used on non-congested area.

    b) It may not be utilized on plots in:1) Congested area where only slum TDR is allowed, and2) Congested area of premium value properties where only heritage TDR is

    allowed.

    3.7.3Development Right Certificate

    The Authority may issue development right certificate (DRC) and give it to the owner inlieu of compensation for the reserved plot. The DRC shall contain the followinginformation:

    a) The built-up area which is equal to gross area of the acquired plot in metersquare or FAR credit to which the owner is entitled;

    b) Place and usage zone from which the DRC is generated (originating plot);

    c) Area on which the FAR credit shall be used (receiving plot); andd) Development right transferred and remaining.

    If the owner of the originating plot constructs the amenity and hands it over to theAuthority free of cost, additional Development right (DR) shall be issued to himequivalent to the area constructed or developed by him and as decided by the Authority.

    Transfer of DRC by the owner may be done by submitting it to the Authority along withan application for endorsement in the name of the proposed new owner.

  • 7/25/2019 CED46(8064)_24112015

    29/218

    Doc: CED 46 (8064)WCNovember 2015

    29

    The Authority may lay down detailed procedure for utilization of TDR with theinvolvement of registered building professionals.

    4 MEANS OF ACCESS

    4.1Every building/plot shall abut on a public/private means of access like streets/roadsduly formed.

    4.2 Every person who erects a building shall not at any time erect or cause or permit toerect any building which in any way encroaches upon or diminishes the area set apartas means of access required in the Code. No buildings shall be erected so as to depriveany other building of the means of access.

    4.3 Width of Means of Access

    The residential plots shall abut on a public means of access like street/road. Plots whichdo not abut on a street/road shall abut/front on a means of access, the width and otherrequirements of which shall be as given in Table 1.

    In no case, development on plots shall be permitted unless it is accessible by a publicstreet of width not less than 6 m.

    Table 1 Width and Length of Means of Access(Clause4.3)

    SlNo.

    Width of Meansof Access

    Length of Meansof Access

    Max

    (1) (2) (3)M m

    i) 6.0 75ii) 7.5 150iii) 9.0 250iv) 12.0 400v) 18.0 1 000vi) 24.0 above 1 000

    NOTEIf the development is only on one side of the means of access,the prescribed widths may be reduced by 1m in each case.

    4.3.1 Other Buildings

    For all industrial buildings, theatres, cinema houses, assembly halls, stadia, educationalbuildings, markets, other buildings which attract large crowd, the means of accessshall not be less than the following:

  • 7/25/2019 CED46(8064)_24112015

    30/218

    Doc: CED 46 (8064)WCNovember 2015

    30

    Width of Meansof Access

    Length of Meansof Access

    m m12.0 20015.0 40018.0 60024.0 above 600

    Further, in no case shall the means of access be lesser in width than the internalaccessways in layouts and subdivision.

    4.3.2 Footpaths andPathways

    4.3.2.1 Footpaths

    Footpath should be normally designed for a pedestrian Level of Service (LOS) B,thereby providing wide pedestrian facilities for pleasant and comfortable walking. Underresource constraint, LOS C may be adopted for deciding the width of footpath mentionedin Table 2. The width of footpaths depends upon the expected pedestrian traffic and maybe fixed with the help of the following norms subject to not being less than 1.8 m.

    Table 2 Capacity of Footpath and Design(Clause4.3.2.1)

    The land use adjacent to roads significantly influences generation of pedestrian traffic.Recommended width of footpath along various land uses are given in Table 3.

    Sl.No.

    Width ofFoothpath

    m

    Design Flow in Number of Persons per hour

    In Both Directions All in one direction

    LOS B LOS C LOS B LOS C

    (1) (2) (3) (4) (5) (6)

    i) 1.8 1 350 1 890 2 025 2 835ii) 2 1 800 2 520 2 700 3 780iii) 2.5 2 250 3 150 3 375 4 725iv) 3 2 700 3 780 4 050 5 670v) 3.5 3 150 4 410 4 725 6 615vi) 4 3 600 5 040 5 400 7 560

  • 7/25/2019 CED46(8064)_24112015

    31/218

    Doc: CED 46 (8064)WCNovember 2015

    31

    Table 3 Required Width of Footpathas per Adjacent Land Use

    (Clause4.3.2.1)

    Sl.No.

    Description Widthm

    i) Minimum free walkway width andresidential/ mixed use areas

    1.8

    ii) Commercial/Mixed Use Areas 2.5

    iii) Shopping Frontages 3.5 to 4.5

    iv) Bus Stops 3

    v) High Intensity Commercial Areas 4

    4.3.2.2 Pathways

    The approach to the buildings from road/street/internal means of access shall bethrough paved pathway of width not less than 1.5 m, provided its length is not more than30 m.

    4.3.2.2.1 In the case of special housing schemes for low income group andeconomically weaker section of society developed up to two storeyed row/clusterhousing scheme, the pedestrian pathway width shall be 3 m subject to provisions of9.4.1(a). The pedestrian pathway shall not serve more than 8 plots on each side of thepathway; the length of the pathway shall be not more than 50 m.

    4.3.3 The length of the main means of access shall be determined by the distance fromthe farthest plot (building) to the public street. The length of the subsidiary accesswayshall be measured from the point of its origin to the next wider road on which it meets.

    4.3.4 In the interest of general development of an area, the Authority may require themeans of access to be of larger width than that required under 4.3and 4.3.1.

    4.3.5 In existing built-up areas in the case of plots facing street/means of access lessthan 4.5 m in width, the plot boundary shall be shifted to be away by 2.25 m from thecentral line of the street/means of accessway to give rise to a new street/means ofaccessway of 4.5 m width.

    4.4 The means of access shall be levelled, metalled, flagged, paved, sewered, drained,channelled, lighted, laid with water supply line and provided with trees for shade to thesatisfaction of the Authority free of encroachment by any structure or fixture so as not toreduce its width below the minimum required under 4.3 and shall be maintained in acondition to the satisfaction of the Authority.

    4.4.1 If any private street or any other means of access to a building is not levelled,metalled, flagged or paved, sewered, drained, channelled, lighted or laid with watersupply line or provided with trees for shade to the satisfaction of the Authority, who may,

  • 7/25/2019 CED46(8064)_24112015

    32/218

    Doc: CED 46 (8064)WCNovember 2015

    32

    with the sanction of the Authority, by written notice require the owner or owners of theseveral premises fronting or adjoining the said street or other means of access orabutting thereon or to which access is obtained through such street or other means ofaccess or which shall benefit by works executed, to carry out any or more of theaforesaid requirements in such manner as he shall direct.

    4.4.2 If any structure or fixture is set upon a means of access so as to reduce its widthbelow the minimum required, the Authority may remove the same further and recoverthe expenses so incurred from the owner.

    4.5 Access from Highways/Important Roads

    No premises other than highway amenities like petrol pumps, motels, etc, shall have anaccess direct from highways and such other roads not less than 52 m in width, which the

    Authority with the approval of the Highway Authority shall specify from time to time. TheAuthority shall maintain a register of such roads which shall be open to public inspectionat all times during office hours. The portion of such roads on which direct access maybe permitted shall be as identified in the Development Plan. However, in the case ofexisting development on highways/other roads referred to above, the operation of thisclause shall be exempted. These provisions shall, however, be subject to the provisionsof the relevant State Highway Act, and National Highway Act.

    4.6 For high rise buildings and buildings other than residential, the following additionalprovisions of means of access shall be ensured:

    a) The width of the main street on which the building abuts shall not be less than12 m and one end of this street shall join another street not less than 12 m inwidth;

    b) The approach to the building and open spaces on all its sides shall be not lessthan 6 m in width and the layout for the same shall be done in consultationwith the Chief Fire Officer of the city and the same shall be hard surfacecapable of taking the mass of fire engine, weighing up to 45 tonnes. The saidopen space shall be kept free of obstructions and shall be motorable.

    c) The main entrance to the plot shall be of adequate width to allow easy accessto the fire engine and in no case shall it measure less than 6 m. The entrancegate shall fold back against the compound wall of the premises, thus leavingthe exterior accessway within the plot free for movement of fire servicevehicle. If the main entrance at the boundary wall is built over, the minimumclearance shall be 4.5 m. A turning radius of 9 m shall be provided for fire

    tender movement.

    4.6.1 Buildings on Podium

    4.6.1.1 Podium is a horizontal projection (platform) extending beyond building line onone or more sides, and may consist of one or more levels (seeFig. 8). Podium may alsobe constructed as an independent structure.

  • 7/25/2019 CED46(8064)_24112015

    33/218

    Doc: CED 46 (8064)WCNovember 2015

    33

    Fig. 8 Building on Podium

    4.6.1.2 Uses permitted

    Podium may be used for the following purposes:

    a) Parking of vehicles; when used for parking, one toilet and urinal for every 50cars shall be provided on the podium floor;

    b) Building maintenance rooms, fire safety control rooms;c) D.G. sets, electric sub-station (which will confirm to required safety

    requirements of Part 8 'Building Services', Section 2 Electrical and Allied

    Installations'), water tank, pump rooms, and effluent treatment plant rooms;d) Air conditioning equipment and other machine used for services and utilities.e) Topmost podium slab which is open to sky may be used as, required

    recreational open space;f) Other habitable uses may be allowed by counting it in FAR subject to light,

    ventilation and fire safety requirements.

    Uses proposed in (a) to (e) above, shall not be counted towards FAR.

    4.6.1.3 Requirements

    Following requirements shall be satisfied for buildings constructed on podium:

    a) A podium may be permitted in a plot of area 1 000 m2or more.b) A podium, if provided with ramp, may be permitted in one or more levels,

    however the total height shall not exceed 30.0 m above ground level.c) In case a podium is not provided with ramp, but provided with car lift only,

    the same may also be permitted in one or more levels, however, the totalheight shall not exceed 9.0 m above ground level.

    d) Requirements for ramp (see Fig. 9A):

  • 7/25/2019 CED46(8064)_24112015

    34/218

    Doc: CED 46 (8064)WCNovember 2015

    34

    1) One way ramp of clear width of minimum 3.0 m and two way rampwith clear width of minimum 6.0 m shall be provided for LMV.

    2) One way ramp of clear width of minimum 4.5 m and two way rampwith clear width of minimum 9.0 m shall be provided for LCV.

    3) One way ramp of clear width of minimum 6 m and two way rampwith clear width of minimum 12.0 m shall be provided for HMV.

    4) Ramp slope shall be 1 in 8.5) After a 40 m length of continuous ramp, a flat surface of minimum 6

    m length shall preferably be provided [see Fig. 9B].6) If podium is accessible to fire engine,minimum 7.5 m wide ramp

    shall be required for fire engine access with maximum slope of 1 in10.

    e) Podium shall not be permitted in required minimum front open space.f) Podium shall be so designed so as to take the load of fire engine, if

    accessed by fire engine.

    4.6.1.4 Requirements for fire engine movement

    a) Buildings having height more than 15 m above ground level shallnecessarily be accessible by fire engine, as follows (seeFig. 10A-1):

    1) For buildings having floor area less than 10 000 m2, fire engineshall have access to at least 1/3 of the perimeter of building.

    2) For buildings having floor area more than 10 000 m2, fire engineshall have an access to at least to 1/2 of the perimeter of building.

    g) Podium may be extended beyond the building line to the extent ofmaximum 11.0 m on the side where fire engine access is provided, ifpodium is not accessible by fire engine (see Fig. 10A-2 and 10A-3). Suchrestriction shall not apply in case podium is accessible by fire engine (Fig.

    10B).b) Minimum 6.0 m driveway width and 9.0 m width at turning shall be

    available for fire engine movement.

  • 7/25/2019 CED46(8064)_24112015

    35/218

    Doc: CED 46 (8064)WCNovember 2015

    35

    Fig. 9A

    Fig. 9 B

    Fig. 9 Ramps in Podium

  • 7/25/2019 CED46(8064)_24112015

    36/218

    Doc: CED 46 (8064)WCNovember 2015

    36

    `

    Fig. 10A-1 Emergency Vehicle Access Requirement in case Podium is notAccessible by Fire Engine

  • 7/25/2019 CED46(8064)_24112015

    37/218

    Doc: CED 46 (8064)WCNovember 2015

    37

    Fig. 10A-2 Extent of Podium Projection Allowed Beyond Building of Sidehaving Fire Engine Access (If Podium is not Accessible by Fire Engine)

  • 7/25/2019 CED46(8064)_24112015

    38/218

    Doc: CED 46 (8064)WCNovember 2015

    38

    Fig. 10A-3 Podium Projection if Podium is not Accessible by Fire Engine

  • 7/25/2019 CED46(8064)_24112015

    39/218

    Doc: CED 46 (8064)WCNovember 2015

    39

    Fig. 10B Emergency Vehicle Access Requirement in case Podium isAccessible by Fire Engine

    4.7 Cul-de-sacs giving access to plots and extending from 150 m to 275 m in lengthwith an additional turning space at 150 m will be allowed only in residential areas,provided cul-de-sacs would be permissible only on straight roads and further providedthe end of cul-de-sacs shall be higher in level than the level of the starting point of suchdead end road. The turning space, in this case shall be not less than 81 m2in area, withno dimension less than 9 m.

    4.8 Intersection of Roads

    For intersection junctions of roads meeting at right angles as well as other than rightangles, the rounding off or cut off or splay or similar treatment shall be done, to the

  • 7/25/2019 CED46(8064)_24112015

    40/218

    Doc: CED 46 (8064)WCNovember 2015

    40

    approval of the Authority, depending upon the width of roads, the traffic generated, thesighting angle, etc, to provide clear sight distance.

    4.9 The building line shall be set back at least 3 m from internal means of access in alayout of buildings in a plot subject to provisions of 8.2.1.

    5 COMMUNITY OPEN SPACES AND AMENITIES

    5.1 Residential and Commercial Zones

    In any layout or sub-division of land measuring 0.3 hectare or more in residential andcommercial zones, the community open spaces shall be reserved for recreationalpurposes which shall as far as possible be provided in one place or planned out for theuse of the community in clusters or pockets.

    5.1.1 The community open spaces shall be provided catering to the needs of area oflayout, population for which the layout is planned and the category of dwelling units.The following minimum provision shall be made:

    a) 15 percent of the area of the layout, orb) 0.3 to 0.4 ha/1 000 persons; for low income housing, the open spaces shall be

    0.3 ha/1 000 persons.

    5.2 No recreational space shall generally be less than 450 m2.

    5.2.1 The minimum average dimension of such recreational space shall be not lessthan 7.5 m; if the average width of such recreational space is less than 24 m, the lengththereof shall not exceed 2.5 times the average width. However, depending on the

    configuration of the site, commonly open spaces of different shapes may be permittedby the Authority, as long as the open spaces provided serve the needs of the immediatecommunity contiguous to the open spaces.

    5.2.2 In such recreational spaces, a single storeyed structure as pavilion or gymnasiaup to 25 m

    2 in area may be permitted; such area may be excluded from FAR

    calculations.

    5.3 Each recreational area and the structure on it shall have an independent means ofaccess. Independent means of access may not be insisted upon if recreational space isapproachable directly from every building in the layout. Further, the building line shall be

    at least 3 m away from the boundary of recreational open space.

    5.4 Industrial Zones

    In the case of sub-division of land in industrial zones of area 0.8 hectare or more, 5percent of the total area shall be reserved as amenity open space which shall also serveas a general parking space; when such amenity open space exceeds 1 500 m

    2, the

    excess area could be utilized for the construction of buildings for banks, canteens,

  • 7/25/2019 CED46(8064)_24112015

    41/218

    Doc: CED 46 (8064)WCNovember 2015

    41

    welfare centers and such other common purposes considered necessary for theindustrial user, as approved by the Authority.

    5.4.1 In all industrial plots measuring 1 000 m2or more in area, 10 percent of the total

    area shall be provided as an amenity open space to a maximum of 2 500 m2. Such anamenity open space shall have a means of access and shall be so located that it couldbe conveniently utilized as such by the persons working in the industry.

    5.5 Other Amenities

    In addition to community open spaces, the layouts shall provide for the amenities asgiven in 5.5.1 to 5.5.6. These provisions may be modified based on specificrequirements, as decided by the Authority.

    5.5.1 Educational Facilities

    Land AreaRequired, Min

    a) Pre-Pr imary to Secondary Educat ion

    1) Pre-primary, nursery school (1 for every 2 500population)

    i) Area per schoolii) Location of pre-primary/nursery school

    0.08 hato be located near apark

    2) Primary school (class 1 to 5) (1 for every 5 000population)

    i) Strength of the school - 500 Studentsii) Area per school

    a) School building areab) Play field area (with a minimum of

    18 m x 36 m to be ensured for effectiveplay)

    0.40 ha0.20 ha0.20 ha

    3) Senior secondary school (class 6 to 12) (1 forevery 7 500 population)

    i) Strength of the school -1 000 Studentsii) Area per school

    a) School building areab) Play field area (with a minimum of

    68 m x 126 m to be ensured for effectiveplay)

    c) Parking area

    1.80 ha0.60 ha1.00 ha

    0.20 ha

  • 7/25/2019 CED46(8064)_24112015

    42/218

    Doc: CED 46 (8064)WCNovember 2015

    42

    4) Integrated school without hostel facility (class 1to 12) (1 for every 90 000 to 100 000 population)

    i) Strength of the school-1 500 Studentsii) Area per school

    a) School building areab) Play field areac) Parking

    iii) Location

    3.50 ha0.70 ha2.50 ha0.30 ha

    To be located near asport facility

    5) Integrated school with hostel facilities (class 1 to12) (1 for every 90 000 to 100 000 population)

    i) Strength of school - 1 500 Studentsii) Area per school

    a) School building areab) Play field areac) Residential (including hostel area)d) Parking area

    iii) Location

    3.90 ha0.70 ha2.50 ha0.40 ha0.30 ha

    To be located near asport facility

    6) School for physically challenged (Class 1 to 12)(1 for every 45 000 population)

    i) Strength of school - 400 studentsii) Area per school

    a) School building areab) Play field areac) Parking area

    iii) Location

    0.70 ha0.20 ha0.30 ha0.20 ha

    To be located near apark or sport facility

    7) School for mentally challenged (1 for every1 000 000)

    i) Area per schoolii) Location of pre-primary/nursery school

    0.20 hato be located near apark and non-noisepolluting zone

    The schools should preferably face service roads and roads with less trafficintensity.

    b) Higher Educat ion General

    1) College (1 for every 125 000 population)

    i) Student strength of college -1 000 to 1 500students

    ii) Area per college 5.00 ha

  • 7/25/2019 CED46(8064)_24112015

    43/218

    Doc: CED 46 (8064)WCNovember 2015

    43

    a) College building areab) Play field areac) Residential (including hostel area)d) Parking area

    1.80 ha2.50 ha0.40 ha0.30 ha

    2) University campus

    Area

    a) Residential (if included) area

    b) Sports and cultural activities

    c) Parks and landscape including greenbelt

    10.00 ha to60.00 ha

    25 percent of totalland area15 percent of totalland area15 percent of totalland area

    c) Techn ical Educat ion

    1) Technical education centre (A) [1 for every1 000 000 population to include 1 industrialtraining institute (ITI) and 1 polytechnic]

    i) Strength of ITI - 400 Studentsii) Strength of polytechnic - 500 Students

    iii) Area per technical education centrea) Area for ITIb) Area for polytechnic

    4.00 ha1.60 ha2.40 ha

    2) Technical education centre (B) (1 for every1 000 000 population to include 1 ITI,1 technical centre and 1 coaching centre)

    Area per technical education centrea) Area for ITIb) Area for technical centrec) Area for coaching centre

    4.00 ha1.60 ha2.10 ha0.30 ha

    d) Professional Educat ion

    1) Engineering college (1 for every1 000 000 population)

    i) Strength of the college - 1500 Studentsii) Area per college 6.00 ha

    2) Medical college (1 for every 1 000 000 population)

    Area of site including space for general hospital 15.00 ha

  • 7/25/2019 CED46(8064)_24112015

    44/218

    Doc: CED 46 (8064)WCNovember 2015

    44

    3) Nursing and paramedic institute (1 for every1 000 000 population)

    Plot area per institute (subject to Nursing Councilof India/Ministry of Health Norms)

    0.20 ha

    4) Veterinary instituteArea As per Veterinary

    Council of India/Ministry of

    Agriculture Norms(subject toavailability of land)

    5) Other professional colleges (1 for every1 000 000 population)

    i) Strength of the college - 250 to 1500students

    ii) Area of sitea) for students strength up to 250 studentsb) additional area of site for every additional

    100 students or part thereof up to totalstrength of 1 000 students

    c) for strength of college from 1 000 to1 500 students

    2.00 ha

    0.50 ha

    6.00 ha

    5.5.2 Health Care Facilities

    Land AreaRequired, Min

    1) Dispensary (1 for every 15 000 population)

    Area 0.08 ha to 0.12 ha

    2) Nursing home, child welfare and maternitycentre (1 for every 45 000 to 100 000

    population)

    i) Capacity - 25 to 30 bedsii) Area 0.20 ha to 0.30 ha

    3) Poly-clinic with some observation beds (1 forevery 100 000 population)

    Area 0.20 ha to 0.30 ha

    4) Intermediate hospital (category-B) (1 for every100 000 population)

    i) Capacity - 80 beds (initially the provision

  • 7/25/2019 CED46(8064)_24112015

    45/218

    Doc: CED 46 (8064)WCNovember 2015

    45

    may be for 50 beds including 20 maternitybeds)

    ii) Total areaa) Area for hospitalb) Area for residential accommodation

    1.00 ha0.60 ha0.40 ha

    5) Intermediate hospital (category-A) (1 for every100 000 population)

    i) Capacity - 200 beds (initially the provisionmay be for 100 beds)

    ii) Total areaa) Area for hospitalb) Area for residential accommodation

    3.70 ha2.70 ha1.00 ha

    6) General Hospital (1 for every 250 000population)

    i) Capacity - 500 beds (initially the provisionmay be for 300 beds)

    ii) Total areaa) Area for hospitalb) Area for residential accommodation

    6.00 ha4.00 ha2.00 ha

    7) Multi-speciality hospital (1 for 100 000population)

    i) Capacity - 200 beds (initially the provisionmay be for 100 beds)

    ii) Total areaa) Area for hospitalb) Area for residential accommodation

    9.00 ha6.00 ha3.00 ha

    8) Speciality hospital (1 for every 100 000population)

    i) Capacity - 200 beds (initially the provisionmay be for 100 beds)

    ii) Total areaa) Area for hospitalb) Area for residential accommodation

    3.70 ha2.70 ha1.00 ha

    9) Family welfare centre(1 for every 50 000population)

    Area 500 m2to 800 m

    2

  • 7/25/2019 CED46(8064)_24112015

    46/218

    Doc: CED 46 (8064)WCNovember 2015

    46

    10) Diagnostic centre (1 for every 50 000 population)

    Area 500 m2to 800 m2

    11) Veterinary hospital for pets and animals (1 forevery 500 000 population)

    Area 0.20 ha

    12) Dispensary for pet animals and birds (1 for every100 000 population)

    Area 300 m2

    13) Rehabilitation centresArea As per requirement

    5.5.3 Socio-cultural facilities

    Land AreaRequired, Min

    1) Community room (1 for every 5 000 population)

    Area 750 m2

    2) Community hall, MANGAL KARYALAYA/KALYANA MANDAPAM/BARAT GHAR/library (1for every 15 000 population)

    Area 2 000 m

    2

    3) Recreational club (1 for every 100 000population)

    Area 10 000 m2

    4) Music, dance and drama centre (1 for every100 000 population)

    Area 1 000 m2

    5) Meditation and spiritual centre (1 for every100 000 population)

    Area 5 000 m2

    6) Socio-cultural centre/Exhibition cum fair ground(1 for every 1 000 000 population)

    Area 15.00 ha

  • 7/25/2019 CED46(8064)_24112015

    47/218

    Doc: CED 46 (8064)WCNovember 2015

    47

    7) Anganwadi- housing area/cluster (1 for every5 000 population)

    Area 200 to 300 m2

    8) Old age home (1 for every 500 000population)

    Area 1 000 m2max,subject to availabilityof land

    9) Religious facilities

    i) at neighbourhood/housing cluster level (1 forevery 5 000 population)

    Area

    ii) at sub-city level in urban extension (1 forevery 1 000 000 population)

    Area

    400 m2

    4.00 ha

    10) Science centre (1 for every 1 000 000population)

    Area As per requirement

    11) International convention centre (1 at city level)

    Area As per requirement

    12) Other Facilities

    i) Orphanage/Children's centre (one each) (1 forevery 1 000 000 population)

    Area

    ii) Care centre for physically/mentally challenged(1 for every 1 000 000 population)

    Area

    iii) Working women/men hostel(1 for every1 000 000 population)

    Area

    iv)Adult education centre(1 for every1 000 000 population)

    Area

    1 000 m2max,subject to availabilityof land

    1 000 m2max,subject to availabilityof land

    1 000 m2max,subject to availabilityof land

    1 000 m2max,

    subject to availabilityof land

  • 7/25/2019 CED46(8064)_24112015

    48/218

    Doc: CED 46 (8064)WCNovember 2015

    48

    v)Night shelter (1 for every 1 000 000population)Area 1 000 m

    2max,

    subject to availabilityof land

    5.5.4 Distribution Services

    Land AreaRequired, Min

    1) Petrol/diesel filling and servicing centreMay be permitted in central as well as sub-central business district, district centres,community centres (only filling station),residential and industrial use zones in urbanareas, along the national highways, statehighways, villages identified as growth centres,freight complex, proposed major roads andpolice/security force services (for captive useonly)

    i) Locationa) Shall not be located on the road having

    right of way less than 30 m.b) Shall be approved by the explosive/fire

    department.c) Special cases in old city areas may be

    considered based on the approval bystatutory authorities

    ii) Area/Sizea) Only filling stationb) Filling cum service stationc) Filing cum service station cum workshopd) Filling station only for two and three

    wheelers

    30 m x 17 m36 m x 30 m45 m x 36 m18 m x 15 m

    2) Compressed natural gas (CNG) filling centre

    Permitted in all use zones (except in regionalparks and developed district parks) and alongthe national highways, state highways andvillages identified as growth centres, freightcomplex and on proposed major roads

    i) Locationa) Shall not be located on the road having

    right of way less than 30 m.

  • 7/25/2019 CED46(8064)_24112015

    49/218

    Doc: CED 46 (8064)WCNovember 2015

    49

    b) Shall be approved by the explosive/firedepartment.

    ii) Area/Size for CNG mother station (includingbuilding component - control rooms/office/dispensing room/store, pantry and W.C.)

    1 080 m2(36 m x 30 m)

    3) LPG godowns/Gasgodown (1 for every 40 000to 50 000 population)

    The major concern for its storage anddistribution is the location which shall be awayfrom the residential areas and shall have openspaces all around as per the Explosive Rules.

    i) Capacity500 cylinders or 8 000 kg ofLPG

    ii) Area (inclusive of guard room) 520 m2(26 m x 20 m)

    4) Milk distribution booth (1 milk booth for every 5000 population)

    Area inclusive of service area 150 m2

    5) Fruit and vegetable distribution booth (1 boothfor every 5 000 population)

    Area 250m2

    5.5.5 Police, Civil Defence and Home Guards

    Land AreaRequired, Min

    1) Police station (1 for every 90 000 population)

    Area (inclusive of essential residentialaccommodation; 0.05 ha additional to beprovided for civil defence and home guards)

    1.50 ha

    2) Police post (1 for every 40 000 to 50 000population) (not served by a police station)

    Area (inclusive of essential residentialaccommodation)

    0.16 ha

    3) District office and battalion (1 for every1 000 000 population)

  • 7/25/2019 CED46(8064)_24112015

    50/218

    Doc: CED 46 (8064)WCNovember 2015

    50

    Total areai) Area for district office

    ii) Area for battalion

    4.80 ha0.80 ha4.00 ha

    4) Police line (1 for every 2 000 000 population)

    Area 4.00 to 6.00 ha

    5) District Jail (1 for every 1 000 000 population)

    Area 10.00 ha

    6) Civil defence and home guards (1 for every1 000 000 population)

    Area 2.00 ha

    7) Traffic and police control room

    Area As per requirement

    8) Police training institute/college (1 at city level)i) Location - to be located in fringe areasii) Area 5.00 ha

    9) Police firing range (1 at city level)i) Location - to be located in fringe areasii) Area Up to 10.00 ha

    10) Police camp including Central PoliceOrganization/security forces (including Centralsecurity forces)

    Area Up to 10.00 ha

    11) Police booth (to be provided by transportplanners)

    i) Location - at major road intersectionsii) Area 10 to 12 m

    2

    5.5.6 Safety Management

    Land AreaRequired, Min

    1) Fire station (1 for every 200 000 population or 1within 5 to 7 km radius)

    Area inclusive of residential accommodation 1.00 ha

  • 7/25/2019 CED46(8064)_24112015

    51/218

    Doc: CED 46 (8064)WCNovember 2015

    51

    2) Sub fire station/fire post (1 within a radius of 3 to4 km)

    Area inclusive of essential residentialaccommodation

    0.6 ha

    3) Disaster management centre (1 in eachadministrative zone)

    Area 1.00 ha along withsuitable open area

    2.00 ha if softparking, temporaryshelter, paradeground, etcincluded

    4) Fire training institute/college

    Area 3.00 ha

    5.5.7 Telephone, Postal and Banking Facilities

    Land AreaRequired, Min

    a) Telephone and Commun icat ions

    1) Telephone exchange of 40 000 lines (1 for every400 000 population)

    Area 4.00 ha

    2) Radio/TV station (1 for every 500 000 to 800 000population)

    Area 1 700 m2

    3) Remote subscriber unit (RSU) (1 for 3 kmradius)

    Area 300 m2

    b) Postal

    1) Post office counter without delivery (1 for every15 000 population)

    Floor area to be provided in local shoppingcentre

    85 m2

  • 7/25/2019 CED46(8064)_24112015

    52/218

    Doc: CED 46 (8064)WCNovember 2015

    52

    2) Head post office with delivery office (1 for250 000 population)

    Area 750 m2

    3) Head post office and administrative office (1 for500 000 population)

    Area 2 500 m2

    c) Banking

    1) Bank with extension counters with ATM facility(1 for every 15 000 population)

    i) Floor area for countersii) Floor area for ATM

    75 m2

    6 m2

    2) Bank with locker, ATM and other bankingfacilities (1 for 100 000 population)

    Area 2 500 m2

    5.5.8 Sports Facilities

    Land AreaRequired, Min

    1) Divisional sports centre (1 for 1 000 000population)

    Area 20.00 ha

    2) District sports centre (1 for 100 000 population)

    Area 8.00 ha

    3) Neighbourhood play area (1 for 15 000

    population)

    Area 1.50 ha

    4) Residential unit play area (1 for 5 000population)

    Area 5 000 m2

  • 7/25/2019 CED46(8064)_24112015

    53/218

    Doc: CED 46 (8064)WCNovember 2015

    53

    5.5.9 Commercial Centres

    Land AreaRequired, Min

    1) Convenience shopping (1 for every 5 000population)

    Area1 500 m2

    2) Local shopping including service centre (1 forevery 15 000 population)

    Area 4 600 m2

    3) Community centre with service centre (1 forevery 100 000 population)

    Area 5.00 ha

    4) District centre (1 at district level/ 1 for every500000 population)

    Area 40.00 ha

    5) Sub-city centre (1 for every 2 500 000 to5 000 000 population)

    Area As per requirement

    6) City centre (1 for every 5 000 000 pluspopulation)

    Area As per requirement

    7) Local wholesale market/MANDI (1 for 1 000 000population)

    Area 10.00 ha

    8) Weekly markets (1 to 2 locations for every100 000 population with 300 to 400 units perlocation)

    Parking and other open spaces with in thecommercial centres could be so designed thatweekly markets may operate in these areasduring non-working hours.

  • 7/25/2019 CED46(8064)_24112015

    54/218

    Doc: CED 46 (8064)WCNovember 2015

    54

    The area of informal sector should have suitablepublic conveniences and solid waste disposalarrangements.

    Area per location 0.40 ha

    9) Organized informal eating spaces (1 for every100 000 population)

    Area 2 000 m2

    5.5.10 Electrical Sub-station

    Land AreaRequired, Min

    1) 11 kV Sub-station (1 for 15 000 population)

    Area 500 m2

    2) 66 kV Sub-station (2 for 100 000 population)

    Area for each sub-station 6 000 m2

    (that is,60 m x100 m)

    3) 220 kV Sub-station (1 for 500 000 population)

    Area 4.00 ha

    5.5.11 Transport

    Land AreaRequired, Min

    1) Three wheeler and taxi stand (1 for 15 000population)

    Area 500 m2

    2) Bus terminal (1 for 100 000 population)

    Area 4 000 m2

    3) Bus depot (1 for 500 000 population)

    Area 2.00 ha

  • 7/25/2019 CED46(8064)_24112015

    55/218

    Doc: CED 46 (8064)WCNovember 2015

    55

    5.5.12 Cremation/Burial Ground

    The site shall not be in proximity to residential areas and should preferably bein urban extension.

    Land AreaRequired, Min

    1) Electric crematorium (1 for large size towns)

    Area 2.00 ha

    2) Cremation ground (1 for 500 000 population)

    Area 2.50 ha

    3) Burial ground (1 for 500 000 population)

    Area 4.00 ha

    5.5.13 Dhobi Ghat

    Land AreaRequired, Min

    1) Dhobi ghat with appropriate arrangements for

    water and drainage facilities and it shall beensured that the water bodies are not pollutedas a result of such activities (1 for 100 000

    population)

    Area 5 000 m2

    5.6 Every layout or subdivi