  • 7/27/2019 6565323223 Ncp 22

    1/13

    NICMAR - SODE

    ASSIGNMENT

    CONSTRUCTION

    PERSONNEL

    MANAGEMENTNCP 22

    Assignment

    1 Course No -

    2 Course Title -

  • 7/27/2019 6565323223 Ncp 22

    2/13

    3 Assignment No -

    4 Date of Dispatch -

    5 Last Date of Receipt of Assignment at CODE Office -

    ASSIGNMENT:You are a Project Manager on site where work for 3 Km long Tunnel has

    been undertaken. The site is remote and takes about 2 days travel to nearest town.

    Supervisors, technicians & skilled workers are engaged in dangerous / hazardous work.

    Absenteeism due to sickness, quarrels, drinking are adding to less output of work and

    chances of accidents on site are increasing. Management has urged to do something so

    that time targets can be achieved. Discuss how will you tackle the problem and increase

    the output of work.

    Introduction of Main Problem:

    1. Working condition at remote location.

  • 7/27/2019 6565323223 Ncp 22

    3/13

    2. Less productivity & irregularity of workman hampering the project progress.

    3. Involvement of Dangerous / hazardous activity

    4. Absence due to sickness.

    5. Absence due to quarrels & drinks.

    6. Accidents at site.

    Reasons of Various Problems:

    1. Involvement of High risk construction activity

    2. Improper Manpower Management Planning & absenteeism of workmen.

    3. Un-Hygienic surroundings & Temporary Accommodation

    4. Non availability of Medical facilities at the vicinity of the project Site

    5. Availability of Alcohol & Consumption of Alcohol by the Labours

    6. Work related risk of rural construction workers.

    Needs & Their Fulfilments on Site:

    1. Involvement of High risk construction activity

  • 7/27/2019 6565323223 Ncp 22

    4/13

    Proper construction methodology is to be established prior to starting of activity. Design stability

    to be ensured for each supporting / enabling works. Identify risk involvement of each project

    related activity and their impact. Highlight / intimate risk identified and collect the suitable

    economical suggestion through conducting inter brainstorming or consultancy from out side.

    Involvement of human resource to be minimized by identifying alternative automated methods.

    Explore the possibilities of engagement of modern technology applicable for the project work.

    Ensuring the good condition of the machinery involved. Prepare methodology statement

    understandable for frontline supervisor / technician who have more practical knowledge but less

    theoretical knowledge.

    Recommendation for dangerous and hazardous constructing activity:

    o Ensure Preparation of proper construction methodology prior to start.

    o Conduct training for the supervisor / technician on the methodology adopted.

    o Identifying more automated method for carrying out the construction activity.

    o Engage more machinery and reduce manpower involvement as much as possible.

    o Keep equipment in good condition.

    o Ensure the stability of the enabling structure.

    o Regular conduct training for workmen engaged for particular activity.

    2. Improper Manpower Management Planning & absenteeism of workmen:

    Preparation of a proper schedule of Project and assign resources to each task i.e. each activity,

    Assigning resources means identify manpower required for each Task and what is the

    availability of manpower and how much work has been done till date and how much work is

    to be done. Identify type of manpower required i.e. Skilled or unskilled. If manpower is in

  • 7/27/2019 6565323223 Ncp 22

    5/13

    adequate try to get more manpower or try to use the available manpower fully so that

    maximum amount of work to complete and try to complete the urgent works such that it does

    not effect our project duration, reschedule the project and update schedule to head office and

    inform them weekly work progress so that they can help you to overcome the manpower

    problem or try to motivate the available manpower by giving extra benefits if they complete

    the project in time or if manpower is very less than required then immediately inform head

    office so that they can send some more manpower so that the project can run smoothly

    Recommendation for Manpower Management Planning:

    o Manpower planning involved some of steps project manager has to follow the same for

    engagement of manpower, because the Tunnel project is a large project more number of

    manpower is involved in the project .

    o Developing source of manpower supply for all categories of manpower.

    o Understanding the project in all respect and get all details of the project i.e Site condition,

    contract conditions, technical specifications, construction techniques, and time frame

    o Working out the labour component in various parameter of the project, by using

    consultants to work out labour requirement

    o Classifying and categorising labour requirement and various jobs by level of skill,

    responsibility, nature of work etc.

    o Estimation of manpower required in view of the anticipated of absenteeism and labour

    turnover and the stability factor.

    o Ensure the guideline set by the organization for engagement of manpower to be followed.

    The guiding principles are as follows:

    o Care and skill should be exercised in the selection of employees.

  • 7/27/2019 6565323223 Ncp 22

    6/13

    o Introduction to the job should be friendly skilful and adequate.

    o Each employee should be made of feel that his efforts are really appreciated.

    o Consideration should be given to the effect that each rule and instruction may have on the

    feelings of employees.

    o There should be sense of security and reasonable freedom from worry

    o Employees should have a part in planning those things that affect their working

    conditions.

    o Management should be absolutely fair in every policy every practice.

    o Each employee should have a feeling of pride in the worthwhileness of his work and his

    company.

    3. Un-Hygienic surrounding & Temporary Accommodation:

    Before starting of the project management has to well plan because this project is long

    duration so manpower involved will be more it is the one of the preliminary need for the

    employees & workers.

    Un-Hygienic surrounding observed in the project sites are as follows:

    a. Poor drainage condition resulting stagnant water causing growth of mosquito, which

    develop the possibilities of malaria of workmen.

    b. Shallow tube oil for drinking water resulting water diseases.

    c. Improper toilet & latrine facilities for workmen.

    d. Inadequate space for leaving.

  • 7/27/2019 6565323223 Ncp 22

    7/13

    e. Cooking facilities not available towards labour hut

    f. Canteen for food not allotted to labours.

    g. Cleaning of wast material from the colony area.

    Suggestion Methods for Hygiene Factors:

    Management has to well plan for the temporary shelters in such a way that number of workers

    will be involved in the project and how many shelters are required and for different category

    of employees will be working at site and different facility what all materials required for

    construction any how much time required to construct it so that all those thing should be

    completed before starting of project, Management should built temporary shelters for the

    workers who will be working at site because the site is at remote area workers cannot be able

    to say at there and come for work it is the preliminary requirement for the workers so

    management has to take extra precautions, A site office also built with all necessary

    requirements, drinking water should be good because most of diseases are spread by water so

    it is important step to taken care by management.

    4. Non availability of Medical facilities at the vicinity of the project Site

    Management should send a medical team to site and they should stay there till completion of

    project, they should be supplied necessary equipment and medical kits so that they can

    manage any hazardous situation i.e. any sudden accidents they can over come that situation,

    any epidemic occurred they can over come that situation. By this work will be smoothly

    progressed and number of workers absenteeism will be reduced. Worker who is sick will be

  • 7/27/2019 6565323223 Ncp 22

    8/13

    taken care by medical team he will be recovered quickly and he can start doing the work so

    that manpower problem is solved.

    5. Availability of Alcohol & Consumption of Alcohol by the Labours:

    This is the major problem with labour because they drink daily after work so that they get

    some relief from whole days work and body pains, but management should try to avoid

    drinking alcohol or try to get them in limited dose so that they have it in just go for sleep if

    they get it in excess quantities they will be drinking whole night and next day they will be

    absenteeism and also after excess drinking they start quarrelling between themselves its a big

    problem for the project manager while quarrelling their may be any accidents that leads to

    more absenteeism that will also indirectly effect the progress of project. If this quarrelling

    happens regularly then management has to take some precaution steps to handle that problem.

    Such as try to avoid the availability of alcohol near the site so that the labour cannot consume

    much alcohol and this problem is solved and the project may continue smoothly.

    6. Work related risk of rural construction workers.

    The workers are vulnerable not only because they are rural workers who

    do not enjoy the same equal social protection as their urban counterparts.

    They are vulnerable also because they work in the construction industry

    which brings with it a set of risks that are particularly serious for

    construction workers. They are also migrants who are not yet fully

    integrated into urban life and keep distinctive lifestyles. Therefore, even if

    the state policy intends to extend the formal social security schemes to

    these workers, a combination of work related risks, and social risks and

  • 7/27/2019 6565323223 Ncp 22

    9/13

    personal understanding of the risks, often expressed with their status as

    rural-urban migrants, may lead to the failure of a simple extension of

    social security. To understand the challenges better, it is important to

    distinguish work related and status related risks that affect the livelihoods

    of these workers.

    o Some subcontractors deliberately hold the money for a long time to earn

    interest. When a subcontractor mainly hires workers from his home village

    or county, he is more likely to behave in a more responsible way, as he

    has to face the pressure back at home. Late or missing pay is more

    frequent when a subcontractor hires people from outside his home county.

    o Another work related risk is injuries. Construction work involves hard

    labour and operation of heavy equipment. Industrial accidents are

    frequent, especially among poorly trained and inexperienced workers

    Measures to minimize the work related risk:

    o Ensure time release of labour payment and monitor actual payment towards labour involved.

    o Ensure safety standard for protection against industrial injuries.

    Motivation of Employees in Construction Project:

    Motivation is the driving force within individuals that drive them physiologically and

    psychologically to pursue one or more goals to fulfil their needs or expectations. Motivators

    may be intrinsic or extrinsic. An example of an intrinsic motivator is the self-fulfilment of a

    worker as a result of performing a task well.

  • 7/27/2019 6565323223 Ncp 22

    10/13

    Motivation of labour in Construction Project:

    Construction labour can be motivated. This is important because dwindling productivity is a major

    problem confronting construction today. Productivity has decreased every year for the past decade, in

    part because of increasing design complexity, more rigorous federal and state regulations and socio-

    economic changes affecting the work force. Our findings indicate that a highly motivated workforce

    enhances productivity and project effectiveness.

    In construction, the work itself that is, the building of a structure for all to behold is a key motivator

    for all levels of management and the work force. Therefore, a well planned project seems to be the

    first and most important step to achieve good productivity. Unfortunately, on large industrial projects,

    craftsmen often receive only minimal amounts of information about their work . Duplication of

    effort, numerous modifications to plans, schedules that consistently slip makes it difficult to maintain

    a motivated workforce. On large power plant projects, changes in design and problems with material

    availability are considered the major demotivating factors. With effective pre-planning, the

    availability of materials will be checked before workers are assigned to an area so workers do not

    start in one location only to have to be shifted to another location, Care in this respect should improve

    worker motivation and productivity and help promote a high level of accomplishment. Most foremen

    are craftsmen take considerable pride in the work they do. Having to rip out their work and redo it

    can be extremely discomforting. In fact, if it is extensive, redoing parts of a project may be the worst

    de-motivator of all. Craftsmen view overcrowded conditions and crew interference due to extensive

    rework as de-motivating. Worse, such problems can create hostile feelings as a result of the

    frustration. Design standardization can help to minimize rework and improve morale.

    Motivational Programs:

    Although some unique motivational programs were found, the vast majority can be grouped into five

    primary categories: goal setting, incentives, positive reinforcement (i.e., recognition for a job well

    done), worker participation, and work facilitation. The following presents a dissertation on each of

    the five categories discussing first their use in other industries and then their application to

    construction.

  • 7/27/2019 6565323223 Ncp 22

    11/13

    Motivational Technique:

    The motivational techniques are as follows:

    1. A letter of praise from a customer shared directly with the employee who delivered the service.

    2. Provide training to employees. Offer them opportunities to improve themselves.

    3. Involve employees in decisions that directly affect them.

    4. Special Wage increase should be given to employees who do their jobs well.

    5. Provide better job descriptions so that employees will know exactly what is expected of them.

    6. Individual incentive bonuses based upon values that need to be reinforced.

    7. Having good equipment to work with. Good working conditions.

    8. Being trustworthy and respectable.

    9. Job security

    10. Feedback should be constructive and timely.

    Welfare Amenities:

    To mitigate desire productivity the welfare amenities should be ensured towards workmen. The

    following welfare amenities at site for use of workers at scale and standards prescribed below

    1. Canteen

    2. Rest rooms

  • 7/27/2019 6565323223 Ncp 22

    12/13

    3. Night Shelter

    4. Clean drinking water

    5. Latrines and urinals

    6. Washing facilities

    7. First aid facilities

    8. Housing

    9. Crche

    Absenteeism and Turnover:

    The department of Energy study indicated that the absenteeism and turnover are a relatively minor

    concern to workmen. Still, they can have a major impact on total project productivity. High rates of

    absenteeism are a concern, however, to individuals who had to carry extra workloads to compensate

    for missing crewmembers.

    The low job satisfaction resulted in high absence from work and high turnover. Thus absenteeism and

    turnover can be viewed as effects of motivational activities or de-motivational concerns. The cost of

    motivational programs is often by the reduced absenteeism and turnover.

    For example the cost of M2 group Engineering Private Ltd. Big Designing & construction company

    on eight projects has been more than paid for by the reduction in absenteeism and the reduced costs

    associated with hiring some amount per employee to process paper work plus two to three weeks of

    each new employees time to learn the job. Again, the figures on attendance and turnover measure the

    motivational effort that is finally justified. Moreover, awards for good records are perhaps the most

    effective method to decrease absenteeism.

    Recommendation to Management: Considering the project analysis and feasibility study made the

    following recommendation extended towards management -

    1. Deployment of consultant for construction method finalization.

  • 7/27/2019 6565323223 Ncp 22

    13/13

    2. Deployment of Doctor and fast aid centre with adequate medicine facilities.

    3. Arrangement of periodic medical check-up for labours

    4. Proper screening for labour prior to engage them in risk job.

    5. Technical knowledge to be screened for workers.

    6. Identifying more resource pull for workers.

    7. Promoting motivational scheme for labours

    8. Incentive scheme to be implemented for enhancing motivation towards work.

    9. Special care to be taken in account of hygienic aspect of labour hut.

    10. Separate gang to be deployed for maintenance of labour colony.

    11. Remote allowance can be introduce for labours.

    Bibliography :

    1. A Guide to the Project Management Body of Knowledge. William R.Duncan

    2. Management in organization by Koontz and Odoneal, MacGraw Hill

    3. Construction Personnel Management for Construction Industry Managers SODE,

    NICMAR.