    Introduction To The Case

    The case describes the organization and planning of the

    project

    highlights the steps taken by the DMRC to ensure thesuccessful completion of the project

    explains how the DMRC managed the various

    stakeholders like the central and state governments, the

    contractors, and the citizens of Delhi Briefly explains the future plans of the DMRC.

  • 8/8/2019 Delhi Metro Project Grp 4

    3/21

    Learning

    Understand the preliminary activities to be taken up before alarge infrastructure project can be started

    Appreciate the significance of the role of a project managerin project execution

    Understand the importance of the right work culture insuccessful project management

    Recognize the importance of managing the variousstakeholders in a project

    Appreciate the difficulties involved in the execution of largeinfrastructure projects in developing countries, and howthese can be overcome.

  • 8/8/2019 Delhi Metro Project Grp 4

    4/21

    Triggers for MetroTriggers for Metro

    Population of over 1 million.

    More registered vehicles than Mumbai, Kolkata & Chennai

    put together.

    Automobiles contributing to more than two thirds of the

    total atmospheric pollution.

    More than 35 studies recommended Mass Rapid Transit

    System.

  • 8/8/2019 Delhi Metro Project Grp 4

    5/21

    Recommendations ofRites StudyRecommendations ofRites Study

    Commissioned by GNCTD, supported by GOI.

    3 component transit system comprising of

    Rail Corridors (Surface/ Elevated).

    Metro Corridors (Underground).

    Dedicated Busway totaling to 198.50 kms.

    Sequential construction of the total network, due to

    high costs associated.

    16 lines, projected high passenger traffic density

    sections to be constructed first.

  • 8/8/2019 Delhi Metro Project Grp 4

    6/21

    Delhi Metro ProjectDelhi Metro Project Phase 1.Phase 1.

    50 50 Joint Venture Co DMRC Ltd. Incorporated recommendations of various other

    civic organizations.

    Phase I to connect Delhis Business, Education &Shopping District.

    Project to cover 340 hectares of land.

    Design & construction of 3 lines Total length 56 kms.

    50 stations.

    3 maintenance depots.

  • 8/8/2019 Delhi Metro Project Grp 4

    7/21

    Financial ReviewFinancial Review

    Estimated cost at Rs 89.27 billion.

    Capital costs borne by GNCTD & GOI.

    Financial IRR less than 3%.

    Capital Structure DMRC Ltd.

    Debt Equity Ratio of 2:1

    Exemption from Excise & Customs Duty. Repayment of JBIC loan through surpluses from

    revenues, property development.

  • 8/8/2019 Delhi Metro Project Grp 4

    8/21

    Management & StructureManagement & Structure DMRC Ltd.DMRC Ltd.

    Mr. Sreedharan as Project Manager & MD.

    Motivated team of professionals.

    Lean structure

    Project Organization.

    Operation & Maintenance.

    Training at Hong Kong Mass Transit Railway Corporation. Employees and Work Culture.

  • 8/8/2019 Delhi Metro Project Grp 4

    9/21

    The Project PlanThe Project Plan

    Individual accountability. Daily monitoring of progress.

    Weekly reviews and targets.

    Delhi Metro Act, 2002

    Superseded Delhi Municipal Laws.

    Lower courts barred from issuing stay orders.

    Dedicated team of lawyers to prevent property disputes.

    Cost centers

    Manpower.

    Energy.

    Material & maintenance.

  • 8/8/2019 Delhi Metro Project Grp 4

    10/21

    The Project PlanThe Project Plan (Contd.)(Contd.)

    Special quality assurance team

    Safety of workers.

    Global bidding program for consultancy and contracts.

    Secured best technology available globally.

    5 member consortium called General Consultants Group.

    Advance planning for utility diversion. Adoption of technologies to make up for lost time and to

    reduce costs.

  • 8/8/2019 Delhi Metro Project Grp 4

    11/21

  • 8/8/2019 Delhi Metro Project Grp 4

    12/21

    ImplementationImplementation -- -- Line 1Line 1 Shahdara to Rithalay Shahdara to Tiz Hazari (7.92 kms)

    y Tis Hazari to Inder Lok (4.74 kms)

    y Inder Lok to Rithala (9.40 kms)

    y Elevated, at-grade

    y 18 stations in total

    y Security - - Barb Wire

    y Shastri Park Kashmiri Gate

    Yamuna (Incremental Launching)

  • 8/8/2019 Delhi Metro Project Grp 4

    13/21

    ImplementationImplementation -- -- Line 2Line 2

    Vishwa Vidyalaya to Central Secretariat

    y Vishwa Vidyalaya to Kashmiri Gate (4 kms)

    y Kashmiri Gate to Central Secretariat (7 kms)

    y 10 stations

    y Cut and Cover Method

    y 7 kms = 4 + 3

  • 8/8/2019 Delhi Metro Project Grp 4

    14/21

    ImplementationImplementation -- -- Line 3Line 3

    Barakhamba to Dwarka Society

    y Revised to extend up to Dwarka Sub-city

    y Schedule and budget was revisedy Changes made to cut costs

    U shaped girders

    Steel replaced cement

    y Intersect with Line 2 at Connaught Place

    y Raja Garden- cross flyover

  • 8/8/2019 Delhi Metro Project Grp 4

    15/21

  • 8/8/2019 Delhi Metro Project Grp 4

    16/21

    Winning the Trust

    Contractors

    o Timely payment

    o Implementation of suggestions

    JBIC Public

    o Advanced planning for Utility Diversion

    o Community Interaction programs to seek suggestionso Temporary accommodations for relocated people

    o Worked in close co-ordination with Delhi Traffic Police

    o Minimize disturbance at nights

  • 8/8/2019 Delhi Metro Project Grp 4

    17/21

    Winning the Trust

    contd CSR

    o

    Pursued environment and safety objectives

    oOHSAS 18001 for Environment, Occupational Healthand Safety Management Systems

    o ISO 14001 for Environment Management

  • 8/8/2019 Delhi Metro Project Grp 4

    18/21

    Road Blocks

    Low Financial IRR prompted second thoughts on the

    project

    Criticism due to inability to recruit, 70% weredeputed from Indian Railways

    Lack of experience & specialized experts in Civil,

    Electrical & Communication Engineering

    Loss of Rs 5 million if one day lost

    Difference of opinion on gauge to be adopted

  • 8/8/2019 Delhi Metro Project Grp 4

    19/21

    Critical Success Factors

    We mean business attitudes.

    Efficiency, courtesy & integrity in corporate culture.

    Corruption free Contract Awarding System & Procurement

    Process.

    Autonomy in decision making.

    Advance planning in utility diversion, minimizing public

    inconvenience.

  • 8/8/2019 Delhi Metro Project Grp 4

    20/21

    Salient FeatureSalient Feature

    Metro Training School at Shastri Park.

    Insistence on at least 1 Indian partner to facilitate

    technology absorption.

    AchievementsAchievements

    Deadline met despite a delay of almost 3 yrs in

    commencement.

    Projected savings of Rs 6 7 billion on project cost.